Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2016 — Statement of Objects and Reasons

Central Electricity Regulatory Commission (Open Access in inter-State Transmission) (Fourth Amendment) Regulations, 2016

Statement of reasonsDated 12 Jul 2016

Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Open Access in inter-State Transmission Regulations, 2008 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Central Electricity Regulatory Commission's Statement of Objects and Reasons for the CERC (Open Access in inter-State Transmission) (Fourth Amendment) Regulations, 2016, dated 12.07.2016 and signed by all four members (p1, p7). It explains why the Commission is replacing Regulation 17 of the 2008 Open Access regulations — the provision fixing the despatch-centre operating charges payable by open access users — and reproduces the final substituted text to be notified in the Gazette (pp6–7).

Pages 1–2 set out the background: the Principal Regulations were notified on 7.2.2008 and amended on 29.5.2009, 11.9.2013 and 12.05.2015; a draft Fourth Amendment with an Explanatory Memorandum was issued on 03.05.2016 for comments; written submissions came from NLDC, PXIL, RPG Power Trading Company and Thermal Powertech; and a public hearing was held on 26.05.2016 at which IEX, PXIL, NLDC and SLDC Chhattisgarh spoke.

Pages 2–3 reproduce the proposed change — levying NLDC charges on scheduled energy rather than per participant — and the comments received: most traders and exchanges supported per-MWh charging with a cap, IEX asking two months to modify its trading software, NLDC preferring a per-day levy and opposing the cap, and SLDC Raipur opposing capping as a precedent for the SERCs.

Pages 4–6 give the Commission's rationale for moving away from a 'cost to serve' basis — changed participant mix, economies of scale, falling scheduling costs on electronic platforms and NLDC's other revenue streams — plus a table of minimum, maximum and average charges actually paid on PXIL and IEX since the May 2015 amendment. The Commission retained the cap so that small open access consumers are not disadvantaged while large-volume transactors are not over-burdened.

Pages 6–7 set out the operative replacement Regulation 17 in six sub-clauses: the flat per-day charge for bilateral transactions at each RLDC/SLDC, the per-MWh NLDC charge on scheduled energy for collective transactions with a daily cap per entity, daily transfer of collected charges to NLDC, a daily reporting duty on power exchanges, the SLDC charge per point of a collective transaction, and the rule that each injection/drawal point counts separately for SLDC charges and intra-State transmission charges.

Standard name
Open Access Regulations
Primary topics
Open access charges, SLDC and RLDC fees and charges, Open access

Read with this

The regulation

Other copies of these documents (6)

Earlier drafts

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document