Open Access in inter-State Transmission (Sixth Amendment) Regulations, 2019

Central Electricity Regulatory Commission (Open Access in inter-State Transmission) (Sixth Amendment) Regulations, 2019

AmendmentDated 12 Dec 2019No. L-7/105(121)/2007-CERC dated 12th December, 2019

Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Open Access in inter-State Transmission Regulations, 2008.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This four-page CERC notification (No. L-7/105(121)/2007-CERC, dated 12 December 2019) makes the Sixth Amendment to the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2008, the "Principal Regulations" (p1). It is the instrument that writes the real-time market into the inter-State open access framework. It comes into force on 1 April 2020 "or such other date as may be notified by the Commission"; no Gazette publication date is printed (p1).

Clause 2 amends the definitions in Regulation 2: it substitutes "Intra-Day Transaction /Contingency Transaction" — same-day or next-day transactions occurring after the day-ahead market window closes, carved back from the real-time market delivery period — and inserts a new "Real-time transactions" definition covering collective transactions on day T or T-1 after the right to revise schedules ends, scheduled by the RLDC or NLDC (p1–2).

Clause 3 adds Regulation 13(B), the operative heart of the amendment: the procedure and timetable for bidding, clearing, scheduling and despatch of the real-time market, including the bidding window that opens the previous evening and repeats every half hour, the nodal agency's indication of available transmission corridor margin before gate closure, a double-sided closed bid auction for each time block, and the nodal agency's announcement of the final schedule (p2). An illustration table on p3 lays out the full auction-to-delivery sequence through three worked daily examples.

Clause 4 adds a proviso to Regulation 15 fixing the order of curtailment: day-ahead transactions are curtailed first, real-time ones after (p3). Clause 5 substitutes Regulation 20(1), requiring state utility and intra-state transactions to be accounted for after real-time-market-driven schedule changes and folded back into the day-ahead net interchange schedules issued by the Regional Load Despatch Centre (p3). A closing Note (p4) records the Principal Regulations and the five earlier amendments and one corrigendum, with their Gazette dates.

Standard name
Open Access Regulations
Primary topics
Open access, Power markets and exchanges, Scheduling and despatch

Read with this

The regulation

Other copies of these documents (6)

Earlier drafts

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.