Open Access in inter-State Transmission (Third Amendment) Regulations, 2015

Central Electricity Regulatory Commission (Open Access in inter-State Transmission) (Third Amendment) Regulations, 2015

AmendmentDated 12 May 2015No.L-7/105(121)/2007-CERC dated 12th May, 2015

Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Open Access in inter-State Transmission Regulations, 2008.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Central Electricity Regulatory Commission's Third Amendment to its 2008 Open Access in inter-State Transmission Regulations, notified on 12 May 2015 (p1). It is short — four amending regulations plus a closing history note — and it does three things.

Regulation 2 inserts two new definitions into Regulation 2(1) of the Principal Regulations. New sub-clause (j-a) defines NLDC and RLDC operating charges as covering fees for scheduling, system operation, and collection and disbursement of charges for short-term open access transactions in inter-State transmission, and makes them additional to fees the Commission specifies under s.28(4) of the Act (p1–2). New sub-clause (o-a) does the same for SLDC operating charges, adding that they apply to inter-State short-term customers only where the concerned State Commission has not notified its own operating charges (p2).

Regulation 3 replaces the second and third provisos to Regulation 8(3)(a), tightening the concurrence process: applicants for bilateral transactions must file a notarised affidavit declaring a valid contract for the power and no other contract for the same power, with an extra declaration for collective transactions before the SLDC (p2–3). It also corrects a cross-reference in the 2013 Second Amendment Regulations (p3).

Regulation 4 substitutes Regulation 17(1) and (2), resetting the per-day operating charges payable by applicants for bilateral transactions and by power exchanges for collective transactions — `1000/- per day or part thereof for each RLDC and each SLDC involved in a bilateral transaction, and for collective transactions `2000/- per day to the NLDC for each State involved plus `1000/- per day per SLDC for each point of transaction (p3).

A closing Note lists when the Principal Regulations and the earlier amendments and corrigendum were gazetted (p3–4).

Standard name
Open Access Regulations
Primary topics
Open access, SLDC and RLDC fees and charges

Read with this

The regulation

Other copies of these documents (6)

Earlier drafts

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.