CERC · Central Electricity Regulatory Commission
Open Access in Inter-State Transmission System Regulations, 2008 — Statement of Reasons
The Central Electricity Regulatory Commission (Open access in inter-State Transmission System) Regulations, 2008
Statement of reasonsDated 4 Mar 2008No.L-7/105(121)/2007-CERC dated 4th March 2008
Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022
See that regulation for the date it took effect and for anything it keeps in force.
The commission's reasons for the Open Access in inter-State Transmission Regulations, 2008 or one of its amendments.
Summary
Summary written by software. Check the regulator's original before you rely on it.
The document is CERC's Statement of Reasons (SoR) for the Central Electricity Regulatory Commission (Open Access in Inter-State Transmission System) Regulations, 2008. It explains why the Commission revamped the 2004 open access regulations (p1), records the consultation on the draft published on 18.12.2007, and states the changes made after 63 stakeholders commented (p2). It is not the operative regulation itself; it is the reasoning and disposition of comments that accompanies the final regulation.
The SoR walks through the main contested design choices. On scheduling, it grants limited flexibility to revise or cancel approved schedules with notice, and explains the associated transmission and operating charge treatment and the removal of nodal-agency discretion for extraordinary circumstances (pp2–4). It retains prior SLDC concurrence through the nodal agency, rejecting suggestions for deemed approval, penalties and a 50% intra-State supply mandate (pp4–6). On curtailment, it adopts pro-rata refunds without a threshold and specifies permitted reasons, while carrying over curtailment for central allocations (pp6–7). It creates a long-term customer definition and says long-term access will continue under the 2004 Regulations until separate regulations (pp7–8).
It then justifies the open access transmission charges, including the lower rate for short-term users and the method for collective transactions, and explains operating charges for RLDCs/SLDCs and the utilisation of transmission charges between CTU and long-term customers (pp8–11). It reports changes to definitions, treatment of transmission losses, complaint redressal, information dissemination, UI/standby charges, and congestion management via e-bidding (pp11–19). Further sections cover the detailed procedure, power exchange issues, miscellaneous stakeholder suggestions and the Competition Commission's comments (pp19–29). The Annexure lists the stakeholders who commented (pp30–31).
Read with this
The regulation
- Dated 25 Jan 2008Open Access in inter-State Transmission Regulations, 2008
Amendments and corrections
- Dated 20 May 2009Open Access in inter-State Transmission (Amendment) Regulations, 2009
- Dated 10 Jun 2009Open Access in inter-State Transmission Regulations, 2008 — Corrigendum, 2009
- Dated 10 Jun 2009Open Access (Amendment) Regulations, 2009 — Corrigenda
- Dated 11 Sep 2013Open Access in inter-State Transmission (Second Amendment) Regulations, 2013
- Dated 12 May 2015Open Access in inter-State Transmission (Third Amendment) Regulations, 2015
- Dated 22 Jun 2016Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2016
- Dated 2 Jan 2019Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018
- Dated 12 Dec 2019Open Access in inter-State Transmission (Sixth Amendment) Regulations, 2019
- Dated 20 Mar 2020Open Access Regulations, 2008 — Sixth Amendment — Commencement Notification, 2020
- Dated 15 Jun 2010Changes some provisions: Sharing of ISTS Charges and Losses Regulations, 2010
- Dated 15 Jun 2010Changes some provisions: Sharing of Inter State Transmission Charges and Losses Regulations, 2010
Commencement notices and reasons
- Dated 1 Jul 2009Open Access in Inter-State Transmission Regulations, 2008 — 2009 Amendment — Statement of Reasons
- Dated 12 May 2015Open Access in inter-State Transmission (Third Amendment) Regulations, 2015 — Statement of Objects and Reasons
- Dated 12 Jul 2016Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2016 — Statement of Objects and Reasons
- Dated 2 Jan 2019Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018 — Statement of Reasons
- Dated 21 Mar 2022Notification — effective date 01.05.2022
- Dated 21 Mar 2022Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018 — Commencement Notification
- Date not statedReal-Time Market Framework — Statement of Reasons
Procedures and orders made under it
- Dated 1 Apr 2022Approval of Procedure for Short Term Open Access in inter-State Transmission System through NOAR, 2022
- Dated 1 Apr 2022Short Term Open Access in Inter-State Transmission through NOAR — Procedure, 2022
- Dated 6 May 2022Corrigendum to the NOAR STOA Procedure Order, 2022
- Date not statedProcedure for Short Term Open Access in inter-State Transmission System through NOAR, 2022
Other copies of these documents (6)
- Dated 25 Jan 2008Open Access in inter-State Transmission Regulations, 2008
- Dated 11 Sep 2013Open Access in inter-State Transmission Regulations, 2008 — Second Amendment, 2013
- Dated 12 May 2015Open Access in inter-State Transmission (Third Amendment) Regulations, 2015
- Dated 22 Jun 2016Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2016
- Dated 2 Jan 2019Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018
- Dated 12 Dec 2019Open Access in inter-State Transmission Regulations, 2008 — Sixth Amendment, 2019
Earlier drafts
- Dated 3 Jul 2014Open Access in inter-State Transmission Regulations, 2008 — Third Amendment, 2014 — Draft
- Dated 3 Jul 2014Public notice: Open Access in inter-State Transmission (Third Amendment) Regulations, 2014 — Public Notice — Draft
- Released with the notice dated 3 Jul 2014Explanatory memorandum: Open Access in inter-State Transmission, 2008 — Third Amendment, 2014 — Explanatory Memorandum — Draft
- Dated 3 May 2016Open Access in inter-State Transmission, 2008 — Fourth Amendment, 2016 — Draft
- Dated 3 May 2016Public notice: Open Access in inter-State Transmission, 2008 — Fourth Amendment, 2016 — Public Notice — Draft
- Released with the notice dated 3 May 2016Explanatory memorandum: Open Access in Inter-state Transmission (Fourth Amendment) Regulations, 2016 — Explanatory Memorandum — Draft
- Dated 8 Aug 2018Open Access in inter-State Transmission Regulations, 2008 — Fifth Amendment, 2018 — Draft
- Released with the notice dated 8 Aug 2018Explanatory memorandum: Open Access in inter-State Transmission, 2008 — Fifth Amendment — Draft Explanatory Memorandum
- Dated 8 Aug 2018Public notice: Draft Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018 — Public Notice
- Dated 6 Aug 2019Open Access in inter-State Transmission Regulations, 2008 — Sixth Amendment, 2019 — Draft
- Released with the notice dated 6 Aug 2019Explanatory memorandum: Real-Time Markets for Electricity — Explanatory Memorandum
2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.