CERC · Central Electricity Regulatory Commission
Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018 — Commencement Notification
Gazette No. 169, effective date 01.05.2022
Commencement noticeDated 21 Mar 2022Published in the Gazette 29 Mar 2022No.L-7/105(121)/2007-CERC dated 21st March, 2022
Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022
See that regulation for the date it took effect and for anything it keeps in force.
Commencement notice for the Open Access in inter-State Transmission Regulations, 2008 or one of its amendments. The dates are in the notice.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a two-page CERC commencement notification. The CERC (Open Access in inter-State Transmission) (Fifth Amendment) Regulations, 2018 were notified on 02.02.2019, but under clause 1.2 of their Regulation 1 they were to come into force only from a date separately notified by the Commission (p2). This notification supplies that date: the Fifth Amendment Regulations, except Clause 9.1, come into force with effect from 01.05.2022 (p2).
Three operative paragraphs manage the transition. Short term open access applicants may apply for registration in NOAR before 1.5.2022 in accordance with the detailed procedure (p2). Applications for short term open access, or Standing clearance, received up to 30.04.2022 continue to be processed under the corresponding pre-amendment provisions of the Principal Regulations (p2). Detailed procedures issued under Regulation 4 of the Principal Regulations also continue in operation till further orders, saved under s.6 of the General Clauses Act, 1897 (p2).
The text is silent on Clause 9.1 — which amends Regulation 8 of the Principal Regulations — and expressly carves it out of this commencement, so its fate is not answered here. The notification is dated 21 March 2022 and was published in the Gazette of India Extraordinary on 29 March 2022 (p1–2).
Read with this
The regulation
- Dated 25 Jan 2008Open Access in inter-State Transmission Regulations, 2008
Amendments and corrections
- Dated 20 May 2009Open Access in inter-State Transmission (Amendment) Regulations, 2009
- Dated 10 Jun 2009Open Access in inter-State Transmission Regulations, 2008 — Corrigendum, 2009
- Dated 10 Jun 2009Open Access (Amendment) Regulations, 2009 — Corrigenda
- Dated 11 Sep 2013Open Access in inter-State Transmission (Second Amendment) Regulations, 2013
- Dated 12 May 2015Open Access in inter-State Transmission (Third Amendment) Regulations, 2015
- Dated 22 Jun 2016Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2016
- Dated 2 Jan 2019Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018
- Dated 12 Dec 2019Open Access in inter-State Transmission (Sixth Amendment) Regulations, 2019
- Dated 20 Mar 2020Open Access Regulations, 2008 — Sixth Amendment — Commencement Notification, 2020
- Dated 15 Jun 2010Changes some provisions: Sharing of ISTS Charges and Losses Regulations, 2010
- Dated 15 Jun 2010Changes some provisions: Sharing of Inter State Transmission Charges and Losses Regulations, 2010
Commencement notices and reasons
- Dated 4 Mar 2008Open Access in Inter-State Transmission System Regulations, 2008 — Statement of Reasons
- Dated 1 Jul 2009Open Access in Inter-State Transmission Regulations, 2008 — 2009 Amendment — Statement of Reasons
- Dated 12 May 2015Open Access in inter-State Transmission (Third Amendment) Regulations, 2015 — Statement of Objects and Reasons
- Dated 12 Jul 2016Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2016 — Statement of Objects and Reasons
- Dated 2 Jan 2019Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018 — Statement of Reasons
- Dated 21 Mar 2022Notification — effective date 01.05.2022
- Date not statedReal-Time Market Framework — Statement of Reasons
Procedures and orders made under it
- Dated 1 Apr 2022Approval of Procedure for Short Term Open Access in inter-State Transmission System through NOAR, 2022
- Dated 1 Apr 2022Short Term Open Access in Inter-State Transmission through NOAR — Procedure, 2022
- Dated 6 May 2022Corrigendum to the NOAR STOA Procedure Order, 2022
- Date not statedProcedure for Short Term Open Access in inter-State Transmission System through NOAR, 2022
Other copies of these documents (6)
- Dated 25 Jan 2008Open Access in inter-State Transmission Regulations, 2008
- Dated 11 Sep 2013Open Access in inter-State Transmission Regulations, 2008 — Second Amendment, 2013
- Dated 12 May 2015Open Access in inter-State Transmission (Third Amendment) Regulations, 2015
- Dated 22 Jun 2016Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2016
- Dated 2 Jan 2019Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018
- Dated 12 Dec 2019Open Access in inter-State Transmission Regulations, 2008 — Sixth Amendment, 2019
Earlier drafts
- Dated 3 Jul 2014Open Access in inter-State Transmission Regulations, 2008 — Third Amendment, 2014 — Draft
- Dated 3 Jul 2014Public notice: Open Access in inter-State Transmission (Third Amendment) Regulations, 2014 — Public Notice — Draft
- Released with the notice dated 3 Jul 2014Explanatory memorandum: Open Access in inter-State Transmission, 2008 — Third Amendment, 2014 — Explanatory Memorandum — Draft
- Dated 3 May 2016Open Access in inter-State Transmission, 2008 — Fourth Amendment, 2016 — Draft
- Dated 3 May 2016Public notice: Open Access in inter-State Transmission, 2008 — Fourth Amendment, 2016 — Public Notice — Draft
- Released with the notice dated 3 May 2016Explanatory memorandum: Open Access in Inter-state Transmission (Fourth Amendment) Regulations, 2016 — Explanatory Memorandum — Draft
- Dated 8 Aug 2018Open Access in inter-State Transmission Regulations, 2008 — Fifth Amendment, 2018 — Draft
- Released with the notice dated 8 Aug 2018Explanatory memorandum: Open Access in inter-State Transmission, 2008 — Fifth Amendment — Draft Explanatory Memorandum
- Dated 8 Aug 2018Public notice: Draft Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018 — Public Notice
- Dated 6 Aug 2019Open Access in inter-State Transmission Regulations, 2008 — Sixth Amendment, 2019 — Draft
- Released with the notice dated 6 Aug 2019Explanatory memorandum: Real-Time Markets for Electricity — Explanatory Memorandum
2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.