Skip to content

CERC · Central Electricity Regulatory Commission

Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2016

Central Electricity Regulatory Commission (Open Access in inter-State Transmission) (Fourth Amendment) Regulations, 2016

Amendment · Gazette copyDated 22 Jun 2016No.L-7/105(121)/2007-CERC dated 22nd June, 2016

Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

The Gazette copy of the Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2016.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Fourth Amendment to CERC's Open Access in inter-State Transmission Regulations, 2008, issued by the Central Electricity Regulatory Commission at New Delhi on 22 June 2016 under section 178 of the Electricity Act, 2003 (p2). It is a single-purpose instrument: Regulation 2 substitutes Regulation 17 of the Principal Regulations in full, replacing the entire operating-charge regime rather than tweaking it (p2).

The substituted Regulation 17 has six sub-clauses (p2). Sub-clauses (1) and (5) fix per-day operating charges payable by the applicant for each Regional Load Despatch Centre and each State Load Despatch Centre involved, for bilateral and collective transactions respectively. Sub-clause (2) makes NLDC operating charges in collective transactions payable by each successful buyer and seller on the basis of energy scheduled at the regional periphery. Sub-clause (3) sets the NLDC rate for collective transactions, requires power exchanges to transfer the collections to NLDC daily, and caps each participant's daily liability. Sub-clause (4) requires power exchanges to furnish NLDC a daily list of successful participants, volumes cleared and charges levied. Sub-clause (6) provides that each injection or drawal point is counted separately for SLDC operating charges and for intra-State transmission charges.

Regulation 1 gives the short title and states that the regulations take effect from the date of publication in the Official Gazette; the Gazette date itself is not printed (p2). The Note on p3 records the notification date of the Principal Regulations (7.2.2008) and of each earlier amendment and corrigendum, giving the history needed to consolidate the text.

Standard name
Open Access Regulations
Primary topics
Open access, SLDC and RLDC fees and charges

Read with this

The regulation

Other copies of these documents (5)

Earlier drafts

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗