Open Access in inter-State Transmission (Second Amendment) Regulations, 2013

Central Electricity Regulatory Commission (Open Access in inter-State Transmission) (Second Amendment) Regulations, 2013

AmendmentDated 11 Sep 2013No.L-7/105(121)/2007-CERC dated 11th September 2013

Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Open Access in inter-State Transmission Regulations, 2008.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Commission amends its 2008 inter-State open access regulations in twelve clauses, issued 11 September 2013 (p1). The regulations take effect from the date of publication in the Official Gazette, but the Gazette date is not printed (p1). Much of the amendment tightens the State-level clearance route into the power market.

Clauses 2 and 3 (pp1–2) add a definition of "intra-day transaction/contingency transaction" — a transaction arising on day T after the day-ahead window closes with delivery on T or T+1, scheduled by RLDC/NLDC — recast the definition of "intra-State entity", delete a reference to a State Transmission Utility from another definition, and replace a reference to "the Grid Code" with "any other regulations made by the Commission".

Clause 3 (pp2–6) rewrites Regulation 8: SLDC-issued "No Objection"/"Prior Standing Clearance" for State utilities and intra-State entities trading through power exchanges and the aggregate MW it covers; its use for collective day-ahead and intra-day/contingency transactions; notarised affidavits on existence of a valid contract and absence of double-selling; deemed clearance where the SLDC does not respond within three working days; and a seven-day debarment the Commission may impose after hearing for breach of the cleared quantum or time.

Clauses 4–9 (pp6–10) cover scheduling on forced outage (by reference to the Grid Code), operating charges on downward revision or cancellation, transmission charges (including a default rate where the State Commission has not determined State-network charges), Special Energy Meter installation, transmission losses, and deviation (unscheduled interchange) charges by reference to the 2009 UI regulations. Clause 11 recasts Regulation 25A to bar short-term open access to willful payment defaulters when the Commission, NLDC or RLDC so directs, and clause 12 substitutes a reference. A closing Note (p11) records where the Principal Regulations, their 2009 amendment and the 2009 corrigendum were published.

Standard name
Open Access Regulations
Primary topics
Open access, Power markets and exchanges, Open access charges

Read with this

The regulation

Other copies of these documents (6)

Earlier drafts

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document