CERC · Central Electricity Regulatory Commission

Draft Sharing of inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2026 — Public Hearing Notice, 2.12.2026

Public hearing on Supplementary Notification to Draft Central Electricity Regulatory Commission (Sharing of inter-State Transmission Charges and Losses) (Fifth Amendment) Regulations, 2026.

Hearing notice on a draftDated 16 Nov 2026L-1/250/2019/CERC dated 16.11.2026

Draft

Voltaic holds no final regulation made from this draft.

Hearing notice on the Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2026 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a one-page CERC public notice (p1) convening an oral public hearing on the Supplementary Notification to the Draft CERC (Sharing of inter-State Transmission Charges and Losses) (Fifth Amendment) Regulations, 2026. The notice, issued on 16.11.2026 under file number L-1/250/2019/CERC, records that the draft supplementary notification was put out on 26.10.2026 and that the written comment window ran to 27.11.2026. The hearing itself is fixed for 2.12.2026, i.e. after the written comments deadline, and the notice states that a Microsoft Teams link will be shared, so participation is contemplated both in person and remotely.

The invitee list is broad — representatives of Central and State Governments, Load Despatch Centres, State Utilities, CPSUs, CTUs, STUs, transmission licensees, trading entities, experts, NGOs, IPPs, financial institutions, consultancy firms and others (p1). Intending participants must send the names of their nominees by 30.11.2026; anyone wishing to present must say so, keep the presentation to 5–10 minutes and 8–10 slides, and email an advance copy by the same date to the two addresses given (p1). The notice is purely procedural: it sets no transmission charges or loss-sharing rules itself, and the substantive content sits in the draft amendment it points to, which is not reproduced here.

Standard name
Sharing of Inter-State Transmission Charges and Losses

Read with this

Other copies of these documents (5)

Earlier drafts

11 more documents belong here and are not on Voltaic: 6 drafts or notices on a draft and 5 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document