Sharing of Inter-State Transmission Charges and Losses Regulations, 2019 — Public Hearing Notice, 29.01.2020

Draft Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2019

Hearing notice on a draftDated 9 Jan 2020No.L-1/250/2019/CERC dated 09.01.2020

Draft

The draft has since been finalised as the Sharing of Inter-State Transmission Charges and Losses Regulations, 2020.

Hearing notice on the Sharing of Inter-State Transmission Charges and Losses Regulations, 2019 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a one-page public notice from the Secretary, Central Electricity Regulatory Commission, dated 09.01.2020 (p1). It records that the Commission issued the Draft Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2019 on 31.10.2019 and invited comments, objections and suggestions up to 31.12.2019 (p1).

The operative purpose is to convene a public hearing on that draft on 29.1.2020 at 10.30 am in the "CERC Court Room" (Fourth Floor), Chanderlok, and to name the stakeholder categories invited — representatives of Central and State Governments, load dispatchers, CPSUs, CTUs, STUs, transmission licensees, trading licensees, power exchanges, NGOs, IPPs and financial institutions (p1).

It sets the logistics for participation: names of proposed participants to be communicated by 24.01.2020, an indication whether the organisation will make a presentation, and a limit on presentations of 5–10 minutes and 8–10 slides (p1). No regulatory obligation is imposed and no substantive transmission-charging rule is stated — it is a consultation-scheduling document only.

Standard name
Sharing of Inter-State Transmission Charges and Losses

Read with this

Other copies of these documents (5)

Proposed changes (drafts with no final yet)

Earlier drafts

11 more documents belong here and are not on Voltaic: 6 drafts or notices on a draft and 5 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document