CERC · Central Electricity Regulatory Commission
Indian Electricity Grid Code (Second Amendment) Regulations, 2013 — Draft
Central Electricity Regulatory Commission (Indian Electricity Grid Code) (Second Amendment) Regulations, 2013
Draft amendmentDated 12 Aug 2013No. L-1/18/2010-CERC dated 12th August, 2013
Draft
A proposal that has since been finalised as the Indian Electricity Grid Code, 2010 — Second Amendment, 2014.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the draft text of a CERC notification, dated 12 August 2013 and numbered No. L-1/18/2010-CERC, that would make the Indian Electricity Grid Code (Second Amendment) Regulations, 2013. It amends the CERC (Indian Electricity Grid Code) Regulations, 2010 — whose notification, addendum, corrigendum and First Amendment are recited in the closing Note (p8) — and is made under section 79(1)(h) read with section 178(2)(g) of the Electricity Act, 2003. It is to take effect on publication in the official Gazette (p1).
Clause 2 adds three definitions to Regulation 2 of the principal regulations — coordinating agency, pooling station and reference rate — building the vocabulary for pooled wind and solar connection (p1–2). Clause 3 amends Regulation 5, deleting the frequency-contingent triggers from the despatch and demand-management sub-regulations, narrowing the frequency band carried in one sub-regulation, and replacing the RLDC direction sub-regulation with a duty to issue standard instantaneous message formats and to receive compliance reports (p2).
Clause 4 is the bulk of the document, rewriting Regulation 6 on scheduling and despatch: notional control areas and day-ahead drawal schedules, pricing of inadvertent deviation through the Deviation Settlement Mechanism, restrictions on state net drawal, revised treatment of ISGS deviation, deletion of three sub-regulations, contingency directions by RLDC and the order in which open access is curtailed, hydro scheduling, deemed revision of schedules on grid disturbance with provisos for region-specific events, the wind scheduling and forecasting regime (with effect from 15.7.2013), and rounding conventions for availability and schedules (p3–6).
Clause 5 amends Annexure 1, the Complementary Commercial Mechanism, setting forecasting and scheduling at pooling-station level, identifying the coordinating agency and its functions, cost sharing, the trigger for pooling stations that grow into the capacity threshold, and the basis of the Reference Rate for Renewable Regulatory Fund computations (p6–8). The amendments pass compliance limits and deviation pricing to the Commission's Deviation Settlement Mechanism and Congestion Charge Regulations rather than fixing them here.
Read with this
The regulation
- Dated 28 Apr 2010Indian Electricity Grid Code Regulations, 2010
Amendments and corrections
- Dated 28 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Corrigendum
- Dated 28 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Addendum
- Dated 5 Mar 2012Indian Electricity Grid Code (First Amendment) Regulations, 2012
- Dated 6 Jan 2014Indian Electricity Grid Code, 2010 — Second Amendment, 2014
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 6 Apr 2016Indian Electricity Grid Code (Fourth Amendment) Regulations, 2016
- Dated 12 Apr 2017Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017
- Dated 5 May 2017IEGC (Fourth Amendment) Regulations, 2016 — Regulation 6.3B Commencement Notification, 2017
- Dated 5 Sep 2019Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017 — Erratum
- Dated 12 Dec 2019Indian Electricity Grid Code (Sixth Amendment) Regulations, 2019
- Dated 20 Mar 2020IEGC Regulations, 2010 — Sixth Amendment, 2019 — Commencement Notification, 2020
- Dated 17 May 2020IEGC Regulations, 2010 — Sixth Amendment — Corrigendum
Commencement notices and reasons
- Dated 18 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Statement of Objects and Reasons
- Dated 6 Mar 2012Indian Electricity Grid Code (First Amendment) Regulations, 2012 — Statement of Objects and Reasons
- Dated 6 Apr 2016Indian Electricity Grid Code, 2010 — Fourth Amendment, 2016 — Statement of Reasons
- Dated 13 Apr 2018Indian Electricity Grid Code (5th Amendment), 2017 — Statement of Reasons
- Date not statedReal-Time Market Framework — Statement of Reasons
Procedures and orders made under it
- Dated 26 Apr 2010Indian Electricity Grid Code, 2010 — Order directing Gazette publication
- Dated 14 Jan 2011Extension of Date of Operation of Clauses 5 and 7 of Annexure-I, IEGC 2010 — Notification
- Dated 14 Jan 2011Extension of date of operation of Clauses 5 and 7 of Annexure-I, IEGC 2010
- Dated 18 Feb 2011Approval of Detailed Procedure for Implementation of Renewable Regulatory Fund Mechanism under IEGC Regulations, 2010
- Dated 5 May 2017Reserve Shut Down and Compensation Mechanism Order, 2017
- Dated 9 Oct 2019Methodology of Settlement of Accounts for Bilateral Short Term and Collective Transactions during Grid Disturbance — Order
Other copies of these documents (9)
- Dated 28 Apr 2010Indian Electricity Grid Code Regulations, 2010
- Dated 5 Mar 2012Indian Electricity Grid Code, 2010 — First Amendment, 2012
- Dated 6 Jan 2014Indian Electricity Grid Code (Second Amendment) Regulations, 2014
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 6 Apr 2016Indian Electricity Grid Code (Fourth Amendment) Regulations, 2016
- Dated 12 Apr 2017Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017
- Dated 5 May 2017IEGC (Fourth Amendment) Regulations, 2016 — Commencement Notification, 2017
- Dated 12 Dec 2019Indian Electricity Grid Code (Sixth Amendment) Regulations, 2019
Earlier drafts
- Released with the notice dated 31 Mar 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015 — Draft
- Dated 2 Jul 2015Draft Indian Electricity Grid Code Regulations, 2015 — Public Notice
- Dated 2 Jul 2015Indian Electricity Grid Code, 2010 — Fourth Amendment Regulations, 2015 — Draft
- Released with the notice dated 9 Dec 2016Indian Electricity Grid Code, 2010 — Fifth Amendment, 2016
- Dated 9 Dec 2016Public notice: Draft Indian Electricity Grid Code (Fifth Amendment) Regulation, 2016 — Public Notice
- Released with the notice dated 9 Dec 2016Explanatory memorandum: Explanatory Memorandum to the IEGC amendments (spinning reserves, ancillary services, un-requisitioned power)
- Dated 6 Aug 2019Indian Electricity Grid Code, 2010 — Sixth Amendment, 2019 — Draft
- Released with the notice dated 6 Aug 2019Explanatory memorandum: Real-Time Markets for Electricity — Explanatory Memorandum
- Released with the notice dated 12 Aug 2013Explanatory memorandum: IEGC (Second Amendment) Regulations, 2013 — Explanatory Memorandum
- Dated 12 Aug 2013Public notice: Indian Electricity Grid Code (Second Amendment) Regulations, 2013 — Public Notice — Draft
3 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft and 1 draft or notice on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.