CERC · Central Electricity Regulatory Commission

Indian Electricity Grid Code (Fourth Amendment) Regulations, 2016

Central Electricity Regulatory Commission (Indian Electricity Grid Code) (Fourth Amendment) Regulations, 2016

AmendmentDated 6 Apr 2016No. L-1/18/2010-CERC dated 6 th April, 2016

Replaced by Indian Electricity Grid Code Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Indian Electricity Grid Code Regulations, 2010.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Fourth Amendment to CERC's Indian Electricity Grid Code (IEGC) Regulations, 2010, notified on 6 April 2016 (p1). It grafts two new substantive regimes onto the Grid Code: a procedure for declaring commercial operation of generating stations and transmission systems, and a "technical minimum" regime under which the system operator may run Central and inter-State generating stations below their normative availability without leaving them uncompensated.

Regulation 6.3A (pp2–7) is the larger addition. It defines the date of commercial operation for thermal units (pp2–3), hydro and pumped-storage units (pp3–5), inter-State transmission elements (pp6–7) and communication systems (p7); specifies how trial runs are conducted, notified to beneficiaries and to RLDCs/SLDCs, certified by the generating company's CMD/CEO/MD and approved by its board, and cleared within a fixed window; and covers de-rating and repeat trials when a unit fails to demonstrate capacity. It also deals with matching of generation and transmission commissioning, dedicated lines, and tariff-based competitive bidding, with CEA monitoring. It states that its trial-operation and COD provisions prevail over the CERC Tariff Regulations, 2014 where the two are inconsistent (p7).

Regulation 6.3B (pp8–10) fixes the technical minimum for unit operation at 55% of MCR (p8), empowers RLDCs to direct stations to operate at or above that minimum but below normative plant availability factor, and sets out the compensation mechanism — station heat rate and auxiliary consumption degradation by unit-loading band, start-up fuel norms for reserve shutdowns beyond seven starts a year, gas-station treatment, annual reconciliation, and who bears the cost. It directs NLDC to draft a Detailed Operating Procedure and RPCs to work out compensation-sharing mechanisms.

Commencement is on gazette publication, except 6.3B, which awaits a separate Commission notification (p1), so the two halves can come into force on different dates.

Standard name
Grid Code
Primary topics
Grid operation and grid code, Scheduling and despatch

Read with this

The regulation

Other copies of these documents (9)

3 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document