CERC · Central Electricity Regulatory Commission
Indian Electricity Grid Code (Fourth Amendment) Regulations, 2016
Central Electricity Regulatory Commission (Indian Electricity Grid Code) (Fourth Amendment) Regulations, 2016
AmendmentDated 6 Apr 2016No. L-1/18/2010-CERC dated 6 th April, 2016
Replaced by Indian Electricity Grid Code Regulations, 2023
See that regulation for the date it took effect and for anything it keeps in force.
Amends the Indian Electricity Grid Code Regulations, 2010.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Fourth Amendment to CERC's Indian Electricity Grid Code (IEGC) Regulations, 2010, notified on 6 April 2016 (p1). It grafts two new substantive regimes onto the Grid Code: a procedure for declaring commercial operation of generating stations and transmission systems, and a "technical minimum" regime under which the system operator may run Central and inter-State generating stations below their normative availability without leaving them uncompensated.
Regulation 6.3A (pp2–7) is the larger addition. It defines the date of commercial operation for thermal units (pp2–3), hydro and pumped-storage units (pp3–5), inter-State transmission elements (pp6–7) and communication systems (p7); specifies how trial runs are conducted, notified to beneficiaries and to RLDCs/SLDCs, certified by the generating company's CMD/CEO/MD and approved by its board, and cleared within a fixed window; and covers de-rating and repeat trials when a unit fails to demonstrate capacity. It also deals with matching of generation and transmission commissioning, dedicated lines, and tariff-based competitive bidding, with CEA monitoring. It states that its trial-operation and COD provisions prevail over the CERC Tariff Regulations, 2014 where the two are inconsistent (p7).
Regulation 6.3B (pp8–10) fixes the technical minimum for unit operation at 55% of MCR (p8), empowers RLDCs to direct stations to operate at or above that minimum but below normative plant availability factor, and sets out the compensation mechanism — station heat rate and auxiliary consumption degradation by unit-loading band, start-up fuel norms for reserve shutdowns beyond seven starts a year, gas-station treatment, annual reconciliation, and who bears the cost. It directs NLDC to draft a Detailed Operating Procedure and RPCs to work out compensation-sharing mechanisms.
Commencement is on gazette publication, except 6.3B, which awaits a separate Commission notification (p1), so the two halves can come into force on different dates.
Read with this
The regulation
- Dated 28 Apr 2010Indian Electricity Grid Code Regulations, 2010
Amendments and corrections
- Dated 28 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Corrigendum
- Dated 28 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Addendum
- Dated 5 Mar 2012Indian Electricity Grid Code (First Amendment) Regulations, 2012
- Dated 6 Jan 2014Indian Electricity Grid Code, 2010 — Second Amendment, 2014
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 12 Apr 2017Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017
- Dated 5 May 2017IEGC (Fourth Amendment) Regulations, 2016 — Regulation 6.3B Commencement Notification, 2017
- Dated 5 Sep 2019Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017 — Erratum
- Dated 12 Dec 2019Indian Electricity Grid Code (Sixth Amendment) Regulations, 2019
- Dated 20 Mar 2020IEGC Regulations, 2010 — Sixth Amendment, 2019 — Commencement Notification, 2020
- Dated 17 May 2020IEGC Regulations, 2010 — Sixth Amendment — Corrigendum
Commencement notices and reasons
- Dated 18 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Statement of Objects and Reasons
- Dated 6 Mar 2012Indian Electricity Grid Code (First Amendment) Regulations, 2012 — Statement of Objects and Reasons
- Dated 6 Apr 2016Indian Electricity Grid Code, 2010 — Fourth Amendment, 2016 — Statement of Reasons
- Dated 13 Apr 2018Indian Electricity Grid Code (5th Amendment), 2017 — Statement of Reasons
- Date not statedReal-Time Market Framework — Statement of Reasons
Procedures and orders made under it
- Dated 26 Apr 2010Indian Electricity Grid Code, 2010 — Order directing Gazette publication
- Dated 14 Jan 2011Extension of Date of Operation of Clauses 5 and 7 of Annexure-I, IEGC 2010 — Notification
- Dated 14 Jan 2011Extension of date of operation of Clauses 5 and 7 of Annexure-I, IEGC 2010
- Dated 18 Feb 2011Approval of Detailed Procedure for Implementation of Renewable Regulatory Fund Mechanism under IEGC Regulations, 2010
- Dated 5 May 2017Reserve Shut Down and Compensation Mechanism Order, 2017
- Dated 9 Oct 2019Methodology of Settlement of Accounts for Bilateral Short Term and Collective Transactions during Grid Disturbance — Order
Other copies of these documents (9)
- Dated 28 Apr 2010Indian Electricity Grid Code Regulations, 2010
- Dated 5 Mar 2012Indian Electricity Grid Code, 2010 — First Amendment, 2012
- Dated 6 Jan 2014Indian Electricity Grid Code (Second Amendment) Regulations, 2014
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 6 Apr 2016Indian Electricity Grid Code (Fourth Amendment) Regulations, 2016
- Dated 12 Apr 2017Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017
- Dated 5 May 2017IEGC (Fourth Amendment) Regulations, 2016 — Commencement Notification, 2017
- Dated 12 Dec 2019Indian Electricity Grid Code (Sixth Amendment) Regulations, 2019
Earlier drafts
- Dated 12 Aug 2013Indian Electricity Grid Code (Second Amendment) Regulations, 2013 — Draft
- Released with the notice dated 12 Aug 2013Explanatory memorandum: IEGC (Second Amendment) Regulations, 2013 — Explanatory Memorandum
- Dated 12 Aug 2013Public notice: Indian Electricity Grid Code (Second Amendment) Regulations, 2013 — Public Notice — Draft
- Released with the notice dated 31 Mar 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015 — Draft
- Dated 2 Jul 2015Draft Indian Electricity Grid Code Regulations, 2015 — Public Notice
- Dated 2 Jul 2015Indian Electricity Grid Code, 2010 — Fourth Amendment Regulations, 2015 — Draft
- Released with the notice dated 9 Dec 2016Indian Electricity Grid Code, 2010 — Fifth Amendment, 2016
- Dated 9 Dec 2016Public notice: Draft Indian Electricity Grid Code (Fifth Amendment) Regulation, 2016 — Public Notice
- Released with the notice dated 9 Dec 2016Explanatory memorandum: Explanatory Memorandum to the IEGC amendments (spinning reserves, ancillary services, un-requisitioned power)
- Dated 6 Aug 2019Indian Electricity Grid Code, 2010 — Sixth Amendment, 2019 — Draft
- Released with the notice dated 6 Aug 2019Explanatory memorandum: Real-Time Markets for Electricity — Explanatory Memorandum
3 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft and 1 draft or notice on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.