Skip to content

CERC · Central Electricity Regulatory Commission

Indian Electricity Grid Code, 2010 — Third Amendment, 2015

Central Electricity Regulatory Commission (Indian Electricity Grid Code) (Third Amendment) Regulations, 2015

Amendment · Gazette copyDated 7 Aug 2015In force from 1 Nov 2015No. 1/14/2015-Reg. Aff. (FSDS) (i)/CERC.— dated 7th August, 2015

Replaced by Indian Electricity Grid Code Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

The Gazette copy of the Indian Electricity Grid Code, 2010 — Third Amendment, 2015.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Third Amendment to the CERC (Indian Electricity Grid Code) Regulations, 2010. It is dated 7 August 2015 and comes into force on 1 November 2015 (p3). Its purpose is to write wind and solar generators that are "regional entities" — i.e. connected to the inter-state transmission system — into the Grid Code's scheduling and despatch machinery, reflecting the variable nature of such generation and the Government of India's renewable thrust (p3).

The amendment works through eleven numbered paragraphs. The Part 1 description of Part 6 (Scheduling and Despatch Code) is rewritten to state that scheduling of regional wind and solar generators is covered (p3). The definition of "Pool Account" is replaced so that it spans deviation charge, reactive energy and congestion charge accounts (p4). Regulation 2.4.5 is substituted so the RPC Secretariat prepares the monthly Regional Energy Account, weekly deviation charge account, reactive energy account and congestion charge account, plus a separate deviation charge account for regional wind and solar generators (p4). RLDC daily grid-performance reports must also cover wind and solar generation (p4).

Regulation 6.2's renewable rescheduling methodology is replaced with one-and-a-half-hourly rescheduling for regional entities, handling of deviations, and metering/telemetry for DSM charges (p4). Regulation 6.4(2)(b) brings wind- and solar-based Ultra Mega Power Projects of 500 MW and above into the scheduling framework (p4). Regulation 6.5(23) sets out mandatory technical and real-time data provision to the RLDC, parallel forecasting by generator and RLDC with the generator bearing the commercial consequences of the forecast it chooses, and a schedule-revision regime with one revision per one-and-a-half-hour slot and a daily cap (p4–5). Annexure-1 requires day-ahead forecasts at 15-minute intervals for the next 24 hours for aggregate capacity of 50 MW and above (p5), delinks deviation charges from frequency and settles them under the DSM Regulations, 2014 (p5), and deletes Paras 6, 7 and 9 of Annexure-1 (p5).

Standard name
Grid Code
Primary topics
Grid operation and grid code, Scheduling and despatch, Deviation settlement (DSM)

Read with this

The regulation

Other copies of these documents (8)

3 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document