Indian Electricity Grid Code, 2010 — Second Amendment, 2014

Central Electricity Regulatory Commission (Indian Electricity Grid Code) (Second Amendment) Regulations, 2014

AmendmentDated 6 Jan 2014In force from 17 Feb 2014No.L-1/18/2010-CERC dated 6 thJanuary, 2014

Replaced by Indian Electricity Grid Code Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Indian Electricity Grid Code Regulations, 2010.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's Second Amendment to the Indian Electricity Grid Code, 2010, issued as Notification No. L-1/18/2010-CERC on 6 January 2014 and brought into force from 17 February 2014 (p1). Its purpose is to re-anchor the grid code's frequency-response, scheduling and deviation provisions to the Deviation Settlement Mechanism.

Paragraph 2 (p1–2) adds two definitions to Regulation 2: 'Deviation Settlement Mechanism Regulations', which points to CERC's DSM Regulations, 2014 and their later amendments, and 'Pooling Station', covering the sub-station where wind or solar generation is pooled, with a proviso treating a distribution company / STU / CTU sub-station as the pooling station where there is no separate one.

Paragraph 3 (p2–3) amends Regulation 5 on frequency response. It rewrites how units must behave when frequency improves or falls (no reduction in generation on improvement below a stated frequency; a percentage increase capped at a ceiling of MCR), deletes the specific frequency triggers embedded in Regulations 5.2 and 5.4.2, substitutes the frequency band in Regulation 5.2(m), and replaces Regulation 5.4.2(g) with a clause requiring RLDCs to issue standard instantaneous message formats for contingency directions and to receive compliance reports.

Paragraph 4 (p3–6) is the bulk. It substitutes the provisions on notional control areas and drawal schedules, on SLDC/SEB restrictions on net drawal and automatic demand management, on ISGS deviation and congestion pricing, on RLDC directions during contingencies and curtailment sequencing, on hydro generation scheduling and daily energy, on deemed revision of schedules during a grid disturbance (with the methodology for bilateral and collective transactions to be framed by the National Power Committee and approved by the Commission), and on revision of declared capability. It deletes several existing sub-regulations. It also substitutes the wind scheduling provision, the rounding/resolution provision, and para 5 of Annexure-1, which deals with wind forecasting liability and the Renewable Regulatory Charge route through the Renewable Regulatory Fund (p6). A Note at p7 records the Gazette publication of the Principal Regulations and its first amendment.

Standard name
Grid Code
Primary topics
Grid operation and grid code, Deviation settlement (DSM), Scheduling and despatch

Read with this

The regulation

Other copies of these documents (9)

3 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.