CERC · Central Electricity Regulatory Commission
Indian Electricity Grid Code, 2010 — Fourth Amendment Regulations, 2015 — Draft
Central Electricity Regulatory Commission (Indian Electricity Grid Code) (Fourth Amendment) Regulations, 2015
Draft amendmentDated 2 Jul 2015No.L-1/18/2010-CERC dated 2 nd July, 2015
Draft
A proposal that has since been finalised as the Indian Electricity Grid Code (Fourth Amendment) Regulations, 2016.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Commission's draft Fourth Amendment to the Indian Electricity Grid Code, 2010, dated 2 July 2015. It builds a procedure around two matters the Code did not previously carry: how an inter-State generating station declares commercial operation, and the floor load at which it can be required to run (p1–2).
Paragraph 2 adds three definitions to Regulation 2 — COD, Trial Operation/Trial Run and Technical Minimum Schedule — each by cross-reference to the new provisions rather than by stating the meaning itself (p1). Paragraphs 3 and 4 amend Regulations 6.1 and 6.2 so that the Code's stated scope covers the COD declaration procedure and the technical minimum schedule (p1–2).
Paragraph 5 inserts a new Regulation 6.3A. Sub-regulation 1 lays down the COD test for thermal units and blocks: demonstration of unit capacity on designated fuel through a successful trial run, clearance from the RLDC or SLDC, notice to beneficiaries or buyers before trial run, a certificate signed by the CMD/CEO/MD covering technical standards, plant and auxiliary systems and permanent supply, instrumentation and protection systems, with board approval to follow within a set period; it also covers partial loading, the demonstrated-capacity threshold for COD, the despatch centre's clearance timeline and the start of scheduling (p2–4). Sub-regulation 2 does the same for hydro, including pumped storage, using peaking capability as the test, with special treatment for pondage/storage stations and run-of-river stations that cannot demonstrate peaking when reservoir or inflow levels are insufficient (p4–6). Sub-regulation 3 defines trial run duration and permitted interruptions, and sub-regulation 4 gives these provisions precedence over the Tariff Regulations, 2014 where they conflict (p6).
The final insertion, Regulation 6.3B, fixes the technical minimum schedule for ISGS, enables RLDC directions to operate below a stated load down to that minimum, and creates a compensation route — subject to prudence check — with a station heat rate degradation table for coal/lignite stations, treatment of start-up fuel for reserve shut-down beyond a stated number of start/stops, a rule on which entity ultimately bears the cost, a PPA requirement for stations outside the Commission's regulation, annual emission reporting and an NLDC-prescribed operating procedure for contingency back-down (p7–8).
Read with this
The regulation
- Dated 28 Apr 2010Indian Electricity Grid Code Regulations, 2010
Amendments and corrections
- Dated 28 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Corrigendum
- Dated 28 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Addendum
- Dated 5 Mar 2012Indian Electricity Grid Code (First Amendment) Regulations, 2012
- Dated 6 Jan 2014Indian Electricity Grid Code, 2010 — Second Amendment, 2014
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 6 Apr 2016Indian Electricity Grid Code (Fourth Amendment) Regulations, 2016
- Dated 12 Apr 2017Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017
- Dated 5 May 2017IEGC (Fourth Amendment) Regulations, 2016 — Regulation 6.3B Commencement Notification, 2017
- Dated 5 Sep 2019Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017 — Erratum
- Dated 12 Dec 2019Indian Electricity Grid Code (Sixth Amendment) Regulations, 2019
- Dated 20 Mar 2020IEGC Regulations, 2010 — Sixth Amendment, 2019 — Commencement Notification, 2020
- Dated 17 May 2020IEGC Regulations, 2010 — Sixth Amendment — Corrigendum
Commencement notices and reasons
- Dated 18 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Statement of Objects and Reasons
- Dated 6 Mar 2012Indian Electricity Grid Code (First Amendment) Regulations, 2012 — Statement of Objects and Reasons
- Dated 6 Apr 2016Indian Electricity Grid Code, 2010 — Fourth Amendment, 2016 — Statement of Reasons
- Dated 13 Apr 2018Indian Electricity Grid Code (5th Amendment), 2017 — Statement of Reasons
- Date not statedReal-Time Market Framework — Statement of Reasons
Procedures and orders made under it
- Dated 26 Apr 2010Indian Electricity Grid Code, 2010 — Order directing Gazette publication
- Dated 14 Jan 2011Extension of Date of Operation of Clauses 5 and 7 of Annexure-I, IEGC 2010 — Notification
- Dated 14 Jan 2011Extension of date of operation of Clauses 5 and 7 of Annexure-I, IEGC 2010
- Dated 18 Feb 2011Approval of Detailed Procedure for Implementation of Renewable Regulatory Fund Mechanism under IEGC Regulations, 2010
- Dated 5 May 2017Reserve Shut Down and Compensation Mechanism Order, 2017
- Dated 9 Oct 2019Methodology of Settlement of Accounts for Bilateral Short Term and Collective Transactions during Grid Disturbance — Order
Other copies of these documents (9)
- Dated 28 Apr 2010Indian Electricity Grid Code Regulations, 2010
- Dated 5 Mar 2012Indian Electricity Grid Code, 2010 — First Amendment, 2012
- Dated 6 Jan 2014Indian Electricity Grid Code (Second Amendment) Regulations, 2014
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 6 Apr 2016Indian Electricity Grid Code (Fourth Amendment) Regulations, 2016
- Dated 12 Apr 2017Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017
- Dated 5 May 2017IEGC (Fourth Amendment) Regulations, 2016 — Commencement Notification, 2017
- Dated 12 Dec 2019Indian Electricity Grid Code (Sixth Amendment) Regulations, 2019
Earlier drafts
- Dated 12 Aug 2013Indian Electricity Grid Code (Second Amendment) Regulations, 2013 — Draft
- Released with the notice dated 12 Aug 2013Explanatory memorandum: IEGC (Second Amendment) Regulations, 2013 — Explanatory Memorandum
- Dated 12 Aug 2013Public notice: Indian Electricity Grid Code (Second Amendment) Regulations, 2013 — Public Notice — Draft
- Released with the notice dated 31 Mar 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015 — Draft
- Dated 2 Jul 2015Draft Indian Electricity Grid Code Regulations, 2015 — Public Notice
- Released with the notice dated 9 Dec 2016Indian Electricity Grid Code, 2010 — Fifth Amendment, 2016
- Dated 9 Dec 2016Public notice: Draft Indian Electricity Grid Code (Fifth Amendment) Regulation, 2016 — Public Notice
- Released with the notice dated 9 Dec 2016Explanatory memorandum: Explanatory Memorandum to the IEGC amendments (spinning reserves, ancillary services, un-requisitioned power)
- Dated 6 Aug 2019Indian Electricity Grid Code, 2010 — Sixth Amendment, 2019 — Draft
- Released with the notice dated 6 Aug 2019Explanatory memorandum: Real-Time Markets for Electricity — Explanatory Memorandum
3 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft and 1 draft or notice on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.