CERC · Central Electricity Regulatory Commission
Indian Electricity Grid Code, 2010 — Third Amendment, 2015 — Draft
Central Electricity Regulatory Commission (Indian Electricity Grid Code) (Third Amendment) Regulations, 2015
Draft amendmentReleased with the notice dated 31 Mar 2015
Draft
A proposal that has since been finalised as the Indian Electricity Grid Code, 2010 — Third Amendment, 2015.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a draft CERC notification proposing the Central Electricity Regulatory Commission (Indian Electricity Grid Code) (Third Amendment) Regulations, 2015 (p1). Its number and the day of the month are left blank, and it states only that it will take effect from the date of publication in the Official Gazette (p1). Its single theme is bringing wind and solar generation into the inter-State grid code's scheduling, forecasting and deviation-settlement machinery.
Clause 2 rewrites the description of the Scheduling and Despatch Code (Part 6) so that it expressly covers wind and solar generators scheduled by RLDCs, and explains why (p1). Clause 3 restates the definition of "Pool Account"; clause 4 makes the RPC Secretariat (or another person notified by the Commission) responsible for preparing the monthly Regional Energy Account, weekly deviation charge account, reactive energy account and congestion charge account, including deviation accounts for RLDC-scheduled wind and solar using SLDC/RLDC data (p1–2). Clause 5 requires each RLDC's daily regional grid performance report to cover wind and solar generation and injection (p2).
Clause 6 replaces the earlier three-hourly rescheduling basis and the Renewable Regulatory charge with one-and-half-hourly rescheduling of RLDC-scheduled wind and solar and handling of their deviations through DSM charges (p2). Clause 7 extends the UMPP entry in the scheduling code to wind- and solar-based projects of 500 MW and above, and clause 8 sets out the forecasting framework: mandatory data submission by generators, forecasts by both generator and RLDC, the generator's option to adopt the RLDC forecast (bearing any commercial impact), central engagement of forecasting agencies by RLDCs, and the rules for revising schedules (p2–3).
Clauses 9 to 11 deal with Annexure-1: forecast intervals and the capacity threshold for day-ahead forecasting, deviation charges for RLDC-scheduled wind and solar delinked from frequency and settled under the CERC Deviation Settlement Mechanism Regulations, and deletion of paragraphs 6, 7 and 9 (p3–4). A closing note lists when the Principal Regulations and the first two amendments were published (p4).
Read with this
The regulation
- Dated 28 Apr 2010Indian Electricity Grid Code Regulations, 2010
Amendments and corrections
- Dated 28 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Corrigendum
- Dated 28 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Addendum
- Dated 5 Mar 2012Indian Electricity Grid Code (First Amendment) Regulations, 2012
- Dated 6 Jan 2014Indian Electricity Grid Code, 2010 — Second Amendment, 2014
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 6 Apr 2016Indian Electricity Grid Code (Fourth Amendment) Regulations, 2016
- Dated 12 Apr 2017Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017
- Dated 5 May 2017IEGC (Fourth Amendment) Regulations, 2016 — Regulation 6.3B Commencement Notification, 2017
- Dated 5 Sep 2019Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017 — Erratum
- Dated 12 Dec 2019Indian Electricity Grid Code (Sixth Amendment) Regulations, 2019
- Dated 20 Mar 2020IEGC Regulations, 2010 — Sixth Amendment, 2019 — Commencement Notification, 2020
- Dated 17 May 2020IEGC Regulations, 2010 — Sixth Amendment — Corrigendum
Commencement notices and reasons
- Dated 18 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Statement of Objects and Reasons
- Dated 6 Mar 2012Indian Electricity Grid Code (First Amendment) Regulations, 2012 — Statement of Objects and Reasons
- Dated 6 Apr 2016Indian Electricity Grid Code, 2010 — Fourth Amendment, 2016 — Statement of Reasons
- Dated 13 Apr 2018Indian Electricity Grid Code (5th Amendment), 2017 — Statement of Reasons
- Date not statedReal-Time Market Framework — Statement of Reasons
Procedures and orders made under it
- Dated 26 Apr 2010Indian Electricity Grid Code, 2010 — Order directing Gazette publication
- Dated 14 Jan 2011Extension of Date of Operation of Clauses 5 and 7 of Annexure-I, IEGC 2010 — Notification
- Dated 14 Jan 2011Extension of date of operation of Clauses 5 and 7 of Annexure-I, IEGC 2010
- Dated 18 Feb 2011Approval of Detailed Procedure for Implementation of Renewable Regulatory Fund Mechanism under IEGC Regulations, 2010
- Dated 5 May 2017Reserve Shut Down and Compensation Mechanism Order, 2017
- Dated 9 Oct 2019Methodology of Settlement of Accounts for Bilateral Short Term and Collective Transactions during Grid Disturbance — Order
Other copies of these documents (9)
- Dated 28 Apr 2010Indian Electricity Grid Code Regulations, 2010
- Dated 5 Mar 2012Indian Electricity Grid Code, 2010 — First Amendment, 2012
- Dated 6 Jan 2014Indian Electricity Grid Code (Second Amendment) Regulations, 2014
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 6 Apr 2016Indian Electricity Grid Code (Fourth Amendment) Regulations, 2016
- Dated 12 Apr 2017Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017
- Dated 5 May 2017IEGC (Fourth Amendment) Regulations, 2016 — Commencement Notification, 2017
- Dated 12 Dec 2019Indian Electricity Grid Code (Sixth Amendment) Regulations, 2019
Earlier drafts
- Dated 12 Aug 2013Indian Electricity Grid Code (Second Amendment) Regulations, 2013 — Draft
- Released with the notice dated 12 Aug 2013Explanatory memorandum: IEGC (Second Amendment) Regulations, 2013 — Explanatory Memorandum
- Dated 12 Aug 2013Public notice: Indian Electricity Grid Code (Second Amendment) Regulations, 2013 — Public Notice — Draft
- Dated 2 Jul 2015Draft Indian Electricity Grid Code Regulations, 2015 — Public Notice
- Dated 2 Jul 2015Indian Electricity Grid Code, 2010 — Fourth Amendment Regulations, 2015 — Draft
- Released with the notice dated 9 Dec 2016Indian Electricity Grid Code, 2010 — Fifth Amendment, 2016
- Dated 9 Dec 2016Public notice: Draft Indian Electricity Grid Code (Fifth Amendment) Regulation, 2016 — Public Notice
- Released with the notice dated 9 Dec 2016Explanatory memorandum: Explanatory Memorandum to the IEGC amendments (spinning reserves, ancillary services, un-requisitioned power)
- Dated 6 Aug 2019Indian Electricity Grid Code, 2010 — Sixth Amendment, 2019 — Draft
- Released with the notice dated 6 Aug 2019Explanatory memorandum: Real-Time Markets for Electricity — Explanatory Memorandum
3 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft and 1 draft or notice on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.