CERC · Central Electricity Regulatory Commission
Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017
Central Electricity Regulatory Commission (Indian Electricity Grid Code) (Fifth Amendment) Regulations, 2017
AmendmentDated 12 Apr 2017In force from 1 May 2017No. L-1/18/2010-CERC dated 12th April, 2017
Replaced by Indian Electricity Grid Code Regulations, 2023
See that regulation for the date it took effect and for anything it keeps in force.
Amends the Indian Electricity Grid Code Regulations, 2010.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Fifth Amendment to the CERC (Indian Electricity Grid Code) Regulations, 2010, issued 12 April 2017 and brought into force on 1 May 2017 (p1). It re-writes or inserts provisions across several parts of the Principal Regulations to give grid-level effect to Ancillary Services — particularly Spinning Reserves and the use of Unrequisitioned Surplus (URS) — and to tighten primary frequency response obligations on generators.
The General Part is touched first: the definition of "Spinning Reserve" is substituted, and the residual interpretive clause is reworded to point at the Act and other CERC regulations (p1–2). Part 1 is extended so that its scheduling and despatch scope expressly covers Ancillary Reserve Services, URS utilisation and Spinning Reserves, and the information flow among generating stations, NLDC, RLDCs, power exchanges and SLDCs (p2). Part 2 makes NLDC the nodal agency for collective transactions and Ancillary Services, adds a coordination function for RLDCs/SLDCs/RPCs in implementing ancillary services and identifying spinning reserves at inter-State level, and adds RLDC/SLDC functions covering operation of ancillary services and maintenance of energy accounts (p2–3).
Part 5 is the operational core. The class of units obliged to provide frequency response is redefined by technology and size — coal/lignite thermal, larger open-cycle/combined-cycle gas stations, and hydro — with the hydro threshold raised (p3). A staged date is set for the gas category. The primary-response clause is replaced with a no-reduction-below-nominal-frequency rule and a droop-based increase up to a ceiling of unit capability (p4), the capability clause now differentiates the instant pick-up percentage by technology, and a new provision bars RLDCs/SLDCs from scheduling beyond ex-bus generation at 100% of installed capacity and bars generators from valve-wide-open operation so a governor margin is preserved, with carve-outs for hydro spillage avoidance and for VWO margin in ancillary scheduling (p5). A proviso adds two-yearly independent third-party testing of governor/response capability, cost-recoverable from generators (p5).
Part 6 changes despatch and market timelines — earlier submission hours and a correction of wording — and inserts clauses governing how an original beneficiary consents to its ISGS selling its share in the market, on a standing or daily basis, and how the resulting gains are shared (p6–7). A new Regulation 6.5(A) sets out the framework for scheduling and commercial settlement of energy exchanged under ancillary services, spinning reserves and URS, cross-referring to the 2015 Ancillary Services Regulations and to a Detailed Procedure to be notified separately by the Commission in consultation with POSOCO (NLDC), and allocating gains between ISGS and beneficiary while protecting the beneficiary from adverse energy-charge impact and leaving fixed charges with the beneficiary (p7–8). A closing note lists the earlier corrigenda, addenda and first-to-fourth amendments to the Principal Regulations (p8).
Read with this
The regulation
- Dated 28 Apr 2010Indian Electricity Grid Code Regulations, 2010
Amendments and corrections
- Dated 28 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Corrigendum
- Dated 28 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Addendum
- Dated 5 Mar 2012Indian Electricity Grid Code (First Amendment) Regulations, 2012
- Dated 6 Jan 2014Indian Electricity Grid Code, 2010 — Second Amendment, 2014
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 6 Apr 2016Indian Electricity Grid Code (Fourth Amendment) Regulations, 2016
- Dated 5 May 2017IEGC (Fourth Amendment) Regulations, 2016 — Regulation 6.3B Commencement Notification, 2017
- Dated 5 Sep 2019Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017 — Erratum
- Dated 12 Dec 2019Indian Electricity Grid Code (Sixth Amendment) Regulations, 2019
- Dated 20 Mar 2020IEGC Regulations, 2010 — Sixth Amendment, 2019 — Commencement Notification, 2020
- Dated 17 May 2020IEGC Regulations, 2010 — Sixth Amendment — Corrigendum
Commencement notices and reasons
- Dated 18 Jun 2010Indian Electricity Grid Code Regulations, 2010 — Statement of Objects and Reasons
- Dated 6 Mar 2012Indian Electricity Grid Code (First Amendment) Regulations, 2012 — Statement of Objects and Reasons
- Dated 6 Apr 2016Indian Electricity Grid Code, 2010 — Fourth Amendment, 2016 — Statement of Reasons
- Dated 13 Apr 2018Indian Electricity Grid Code (5th Amendment), 2017 — Statement of Reasons
- Date not statedReal-Time Market Framework — Statement of Reasons
Procedures and orders made under it
- Dated 26 Apr 2010Indian Electricity Grid Code, 2010 — Order directing Gazette publication
- Dated 14 Jan 2011Extension of Date of Operation of Clauses 5 and 7 of Annexure-I, IEGC 2010 — Notification
- Dated 14 Jan 2011Extension of date of operation of Clauses 5 and 7 of Annexure-I, IEGC 2010
- Dated 18 Feb 2011Approval of Detailed Procedure for Implementation of Renewable Regulatory Fund Mechanism under IEGC Regulations, 2010
- Dated 5 May 2017Reserve Shut Down and Compensation Mechanism Order, 2017
- Dated 9 Oct 2019Methodology of Settlement of Accounts for Bilateral Short Term and Collective Transactions during Grid Disturbance — Order
Other copies of these documents (9)
- Dated 28 Apr 2010Indian Electricity Grid Code Regulations, 2010
- Dated 5 Mar 2012Indian Electricity Grid Code, 2010 — First Amendment, 2012
- Dated 6 Jan 2014Indian Electricity Grid Code (Second Amendment) Regulations, 2014
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 7 Aug 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015
- Dated 6 Apr 2016Indian Electricity Grid Code (Fourth Amendment) Regulations, 2016
- Dated 12 Apr 2017Indian Electricity Grid Code (Fifth Amendment) Regulations, 2017
- Dated 5 May 2017IEGC (Fourth Amendment) Regulations, 2016 — Commencement Notification, 2017
- Dated 12 Dec 2019Indian Electricity Grid Code (Sixth Amendment) Regulations, 2019
Earlier drafts
- Dated 12 Aug 2013Indian Electricity Grid Code (Second Amendment) Regulations, 2013 — Draft
- Released with the notice dated 12 Aug 2013Explanatory memorandum: IEGC (Second Amendment) Regulations, 2013 — Explanatory Memorandum
- Dated 12 Aug 2013Public notice: Indian Electricity Grid Code (Second Amendment) Regulations, 2013 — Public Notice — Draft
- Released with the notice dated 31 Mar 2015Indian Electricity Grid Code, 2010 — Third Amendment, 2015 — Draft
- Dated 2 Jul 2015Draft Indian Electricity Grid Code Regulations, 2015 — Public Notice
- Dated 2 Jul 2015Indian Electricity Grid Code, 2010 — Fourth Amendment Regulations, 2015 — Draft
- Released with the notice dated 9 Dec 2016Indian Electricity Grid Code, 2010 — Fifth Amendment, 2016
- Dated 9 Dec 2016Public notice: Draft Indian Electricity Grid Code (Fifth Amendment) Regulation, 2016 — Public Notice
- Released with the notice dated 9 Dec 2016Explanatory memorandum: Explanatory Memorandum to the IEGC amendments (spinning reserves, ancillary services, un-requisitioned power)
- Dated 6 Aug 2019Indian Electricity Grid Code, 2010 — Sixth Amendment, 2019 — Draft
- Released with the notice dated 6 Aug 2019Explanatory memorandum: Real-Time Markets for Electricity — Explanatory Memorandum
3 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft and 1 draft or notice on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.