CERC · Central Electricity Regulatory Commission

Indian Electricity Grid Code (Second Amendment) Regulations, 2014

Central Electricity Regulatory Commission (Indian Electricity Grid Code) (Second Amendment) Regulations, 2014

Amendment · Gazette copyDated 6 Jan 2014In force from 17 Feb 2014No. L-1/18/2010-CERC dated 6th January, 2014

Replaced by Indian Electricity Grid Code Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

The Gazette copy of the Indian Electricity Grid Code, 2010 — Second Amendment, 2014.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Central Electricity Regulatory Commission (Indian Electricity Grid Code) (Second Amendment) Regulations, 2014, issued by CERC on 6 January 2014 under s.79(1)(h) read with s.178(2)(g) of the Electricity Act, 2003, amends the CERC (Indian Electricity Grid Code) Regulations, 2010 and its first amendment (together "the Principal Regulations"). It comes into force on 17-2-2014 (p1).

Regulation 2 inserts new definitions into Regulation 2 of the Principal Regulations — including the Deviation Settlement Mechanism Regulations and a definition of "Pooling Station", with a proviso covering wind/solar generators connected through common feeders and terminating at a discom/STU/CTU sub-station (p1–2).

Regulation 3 rewrites frequency-response provisions in Regulation 5: it restates the primary response requirement on frequency fall, deletes several low-frequency triggers (49.8 Hz, 49.7 Hz) from the demand-management sub-regulations, changes the frequency dead-band figures in Regulation 5.2(m), and substitutes Regulation 5.4.2(g) so RLDCs devise standard instantaneous message formats for contingency directions, backed by compliance reporting (p2).

Regulation 4 is the bulk and substitutes numerous sub-regulations of Regulation 6 on scheduling and despatch: notional control areas and drawal schedules (6.4.6), restriction of net drawal and use of automatic/manual demand management (6.4.7), ISGS deviation limits (6.4.10), deletion of 6.4.11 and 6.4.15, RLDC contingency directions and curtailment ordering (6.4.12), hydro scheduling (6.4.24, 6.5.13), deemed revision of schedules on grid disturbance and NPC settlement methodology (6.5.17), revision of declared capability (6.5.18), wind scheduling thresholds and revision windows (6.5.23), and rounding resolutions for availability, entitlements and schedules (6.5.34) (p2–4).

Paragraph 5 of Annexure-1 (Complimentary Commercial Mechanism) is substituted: wind generators forecast their generation, bear UI charges outside the deviation band, and the host state bears deviation charges within it, shared nationally through a Renewable Regulatory Charge operated via a Renewable Regulatory Fund — applicable from a date to be notified by the Commission (p4).

Standard name
Grid Code
Primary topics
Grid operation and grid code, Scheduling and despatch, Deviation settlement (DSM)

Read with this

The regulation

Other copies of these documents (8)

3 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document