Indian Electricity Grid Code Regulations, 2010

Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2010

RegulationDated 28 Apr 2010In force from 3 May 2010No. L-1/18/2010-CERC dated 28th April 2010

Replaced by Indian Electricity Grid Code Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software, from pages 1 to 36 of 77. Check the regulator's original before you rely on it.

The document is CERC's Indian Electricity Grid Code, 2010, issued in New Delhi on 28 April 2010 and expressed to come into force on 3 May 2010, superseding the Indian Electricity Grid Code, 2006 (p1). It is a principal regulation under Electricity Act 2003 s.79(1)(h) read with s.178(2)(g), and is framed as a single set of technical and commercial rules for all users of the inter-State transmission system, the National and Regional grids, and the load despatch and planning institutions around them (pp10-11).

The notification and short-title, extent and commencement clauses occupy p1. Pages 1-9 are the definitions section, defining grid-operation, scheduling, access and institutional terms such as user, beneficiary, ISGS, ISTS, ATC, ex-power plant, governor droop, regional entity and unscheduled interchange.

Part 1 (pp10-14) sets the IEGC's objective and structure, identifies the entities bound, gives special treatment to DVC, BBMB and SSP, treats an interconnected neighbouring country as a separate control area, and creates compliance oversight: RLDCs and RPCs monitor and report non-compliance, any person may petition CERC, and CERC may act suo motu (pp13-14).

Part 2 (pp15-22) describes the roles and linkages of NLDC, RLDC, RPC, CTU, CEA, SLDC and STU, largely restating their statutory functions and designating nodal agencies for collective transactions, short-term open access, connectivity/long-term access/medium-term open access, energy accounting and transmission availability certification.

Part 3 (pp23-28) is the Planning Code for inter-State transmission: planning objectives and scope, planning process, reliance on CEA perspective plans, Electric Power Survey and transmission planning criteria, planning data exchange, planning criteria for contingency outages and reactive compensation, and implementation through the CERC connectivity/access regulations.

Part 4 (pp29-31) is the Connection Code: procedure and agreement for new or modified ISTS connection, minimum technical requirements for reactive power compensation, data and communication facilities, system recording instruments, safety responsibilities, cyber security framework, international connections and annual asset schedules.

Part 5 begins on p32 and is the Operating Code. The supplied text covers operating philosophy, system security, restrictions on deliberate isolation or opening of important grid elements, reporting of trippings and outages, governor action and restricted governor mode for large thermal and hydro units, limits on suppressing governor action, AVR/PSS obligations, protection coordination and under-frequency/df/dt load shedding. The content list at pp12-13 shows Part 5 also covers demand estimation, demand management, periodic reports, operational liaison, outage planning, recovery procedures and event reporting. Part 6 is to cover day-ahead and intra-day scheduling, open-access transactions and renewable wind/solar scheduling. The full document is 77 pages.

Standard name
Grid Code
Primary topics
Grid operation and grid code, Scheduling and despatch, Network planning and investment

Read with this

Other copies of these documents (9)

3 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.