Indian Electricity Grid Code Regulations, 2010 — Statement of Objects and Reasons

Statement of Objects and Reasons

Statement of reasonsDated 18 Jun 2010

Replaced by Indian Electricity Grid Code Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Indian Electricity Grid Code Regulations, 2010 or one of its amendments.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software, from pages 1 to 51 of 102. Check the regulator's original before you rely on it.

This is the Central Electricity Regulatory Commission's Statement of Objects and Reasons, dated 18 June 2010, for the CERC (Indian Electricity Grid Code) Regulations, 2010 (p1). It explains how the draft grid code, published for comment by public notice dated 12 February 2010, was finalised after comments from 30 stakeholders and a public hearing on 15 March 2010 (p1–2). It is an explanatory record, not the binding grid code; the operative regulations are the ones notified in the Gazette (p2).

Pages 2–8 deal with glossary and definitions. The Commission explains which IEGC 2006 definitions were removed, which were added or modified — including black start procedure, bulk consumer, inter-State transmission system, load, protection sub-committee and regional energy account — and which suggestions it declined, such as definitions for gaming, emergency/grid security and various wind-farm terms (p2–8).

Pages 8–16 cover Chapter 1 matters: the description of the power system, the objective (adding ancillary services and power-market facilitation while retaining renewable integration), the scope (including STU/CTU and DVC arrangements), and non-compliance. On non-compliance, the Commission shifts primary reporting responsibility to RLDCs, with the RPC Member Secretary able to report unresolved issues, and rejects suggestions to soften or delay reporting (p8–16).

Pages 16–23 record decisions on institutional roles: NLDC, RLDC, RPC, CTU, CEA and SLDC. Most roles are retained as per the Electricity Act and existing CERC regulations, with limited additions such as NLDC functions for collective transactions and disaster management, and expanded RPC accounts (p16–23).

Pages 23–29 cover the Planning Code. The Commission discusses TTC/ATC/TRM methodology, planning objectives and scope, planning philosophy, criteria, planning data and implementation of transmission plans. It adds operational feedback from RPCs/NLDC/RLDC and requires transmission planning to take account of renewable evacuation and MNRE capacity-addition plans (p23–29).

Pages 30–39 cover connectivity. Following CEA's objection, the Commission removes detailed technical connectivity and wind-generator provisions from the Grid Code and defers to CEA's Technical Standards for connectivity and CERC's 2009 connectivity regulations (p30–36). It nevertheless suggests features for CEA to consider for wind generators connected at 33 kV and above where collective capacity exceeds 10 MW, including active-power limiting, ramp capability, power factor, fault ride-through, protection, communication and transformer configuration (p35–39).

Pages 40–51 cover operating and system-security issues. The Commission retains governor-action and droop provisions in the Grid Code, modifies restricted governor mode to start at 50.2 Hz instead of 50 Hz, exempts hydro stations with pondage up to three hours, and addresses load-variation limits (p40–44). On frequency, it rejects requests to defer tightening the band and confirms the 49.5–50.2 Hz band, supporting the decision with frequency-profile data for the NEW and SR grids (p45–50).

Standard name
Grid Code
Primary topics
Grid operation and grid code, Network planning and investment, Connectivity and GNA

Read with this

The regulation

Other copies of these documents (9)

3 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.