Skip to content

CERC · Central Electricity Regulatory Commission

Connectivity, Long-Term Access and Medium-Term Open Access to the Inter-State Transmission Regulations, 2009 — Statement of Reasons

In the matter of Central Electricity Regulatory Commission (Grant Of Connectivity, Long-Term Access And Medium-Term Open Access To The Inter-State Transmission And Related Matters) Regulations, 2009

Statement of reasonsDated 30 Oct 2009

Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software, from pages 1 to 39 of 41. Check the regulator's original before you rely on it.

This is CERC’s Statement of Reasons for the final CERC (Grant of Connectivity, Long-Term Access and Medium-Term Open Access to the Inter-State Transmission and Related Matters) Regulations, 2009. It records comments received after a public notice dated 2 March 2009 and a hearing on 31 March 2009 (p1), and explains the Commission’s decisions regulation by regulation.

The general section (pp1–7) addresses whether connectivity and long-term/medium-term access should be separate, why real-time UI and misuse issues are left to other instruments, the scope of “open access” and the duration bands, the gap between 3-year medium-term access and 12-year long-term access, transmission planning triggers, and treatment of existing beneficiaries. It confirms that medium-term open access uses existing margins, is processed by a different nodal agency, and has priority over short-term open access (p6). It also sets eligibility thresholds for connectivity: generating stations of installed capacity 250 MW and above, captive generators with exportable capacity 250 MW and above, and bulk consumers with connected load 100 MW and above (p7).

From p7 onward the statement follows the draft regulation numbers. It discusses definitions and new definitions (Reg 2, pp7–9); scope, nodal agency CTU and application filing (Regs 3–5, pp9–10); application fees and processing timelines (Regs 6–7, pp10–13); grant of connectivity and dedicated-line changes (Reg 8, pp13–16); criteria and priority for long-term access/medium-term open access (Reg 9, pp16–18); interface meters (Reg 11, pp18–19); long-term access applications, system studies, transmission-charge estimates and agreements (Regs 12–15, pp19–24); information to RLDC/SLDC, renewal and relinquishment (Regs 16–18, pp24–28); medium-term open access applications, studies, grant, dedicated line and exit (Regs 19–24, pp28–32); curtailment priority (Reg 25, pp32–33); transmission charges (Reg 26, pp33–35); detailed procedure (Reg 27, pp35–37); payment of charges (Reg 29, pp37–38); UI charges (Reg 30, p38); transmission losses (Reg 31, p39); and redressal (Reg 32, p39).

Standard name
Connectivity and GNA Regulations, Open Access Regulations
Primary topics
Connectivity and GNA, Open access, Transmission tariff

Read with this

Other copies of these documents (7)

Earlier drafts

4 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document