Skip to content

CERC · Central Electricity Regulatory Commission

Revised Procedure for Grant of Connectivity to Projects based on Renewable Sources to ISTS

REVISED PROCEDURE FOR "GRANT OF CONNECTIVITY TO PROJECTS BASED ON RENEWABLE SOURCES TO INTER-STATE TRANSMISSION SYSTEM"

ProcedureDate not stated

Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Made under the Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software, from pages 1 to 46 of 55. Check the regulator's original before you rely on it.

This document is the Revised Procedure issued by the Central Transmission Utility (CTU) for granting connectivity to renewable energy projects to the inter-State transmission system (ISTS). It is issued under Regulation 27 of the CERC Connectivity Regulations, 2009, and supersedes the Detailed Procedure dated 15.5.2018 (p1). The Procedure applies to renewable energy generating stations, renewable power park developers, renewable energy implementing agencies and stand-alone storage projects, and to CTU, RLDCs, SLDCs, STUs, distribution companies and renewable energy implementing agencies (p1). Connectivity is processed in two stages — Stage-I and Stage-II — which may be applied for separately or simultaneously (p1).

The operative part (Clauses 4–16, pp2–15) sets eligibility, the transition of existing bank guarantees from the pre-revised regime, the online application process with formats, timelines for CTU to grant Stage-I connectivity, monitoring obligations, Stage-II eligibility criteria (including Letter of Award or PPA, or land and financial closure milestones), the processing and grant of Stage-II connectivity, bank guarantee requirements, technical requirements for dedicated transmission lines and pooling stations, enhancement of connectivity, sharing of dedicated transmission infrastructure, utilisation monitoring, and coordination with agencies (pp2–15).

The remaining pages (pp16–46+) contain the prescribed FORMATs: affidavit, Stage-I and Stage-II application forms, intimation formats, monitoring status formats, enhancement application, bank guarantee proforma and a model agreement between a lead generator and other generators for sharing a single connection point. The document is a key procedural instrument for renewable energy developers seeking ISTS connectivity.

Standard name
Connectivity and GNA Regulations
Primary topics
Connectivity and GNA, Technical standards, Network planning and investment

Read with this

Other copies of these documents (7)

Earlier drafts

4 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗