CERC · Central Electricity Regulatory Commission
Procedure for Making Application for Grant of Connectivity in ISTS, 2009
PROCEDURE FOR MAKING APPLICATION FOR GRANT OF CONNECTIVITY IN ISTS
ProcedureDated 31 Dec 2009In force from 1 Jan 2010No.–L-1/(3)/2009-CERC dated 31st December, 2009
Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022
See that regulation for the date it took effect and for anything it keeps in force.
Made under the Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009.
Summary
Summary written by software, from pages 1 to 53 of 133. Check the regulator's original before you rely on it.
This is a CERC order dated 31 December 2009 (p1) approving the Central Transmission Utility’s detailed procedure for applications for connectivity to the inter-State transmission system. The order recites Regulation 27(1) of the CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009, which required CTU to submit a detailed procedure after public consultation (p1–2). CTU submitted its draft on 9 November 2009 with stakeholder comments (p2). CERC approves the procedure titled “Procedure for making application for grant of connectivity in ISTS” as the Annexure and directs CTU to give it wide publicity (p2). It also directs that the 2009 Regulations come into force w.e.f. 1 January 2010 and that CTU operationalise the procedure from the same date (p2–3).
The annexed procedure at pp4–10 is the operational core. Section 1 sets scope: applications for connectivity received by CTU on or after the notified commencement; eligible applicants are generating stations, including captive plants, of 250 MW and above and bulk consumers seeking at least 100 MW from ISTS; CTU/POWERGRID is the nodal agency; a connection agreement or tripartite agreement is required before physical interconnection (p4–5). Section 2 lists project-preparedness information generators must file—land, environmental clearance, forest clearance, fuel and water linkage—supported by an affidavit in FORMAT-CON-1 (p5–6). Section 3 prescribes submission by sealed envelope, the application format CON-2, and a non-refundable fee slab tied to quantum of power (p6–7). Section 4 governs changes: material location changes or capacity changes above 100 MW require a fresh application with fee forfeiture and possible cancellation; minor changes use a revised CON-2 (p7). Section 5 sets CTU processing, interconnection study under the CEA Technical Standards for Connectivity to the Grid Regulations, 2007, a 60-day intimation in CON-3, additional data in CON-4 and connection details in CON-5 before signing CON-6 (p7–8). Section 6 provides that connectivity alone does not allow power interchange; long-term access, medium-term open access or short-term open access is separately required, with a commissioning/infirm-power exception subject to RLDC permission (p8–9). Section 7 covers dedicated transmission systems, exemptions for large thermal and hydro stations, cost deposits and bank guarantees (p9–10). Section 8 covers indemnity, applicant-borne costs, compliance with the Electricity Act and CERC regulations, review by the nodal agency with prior CERC approval, and complaints to CERC (p10).
Formats and annexures at pp11–53 include the affidavit, application, grant intimation, additional connection information with schedules and IEEE/PSS/E excitation data annexures, connection offer letter, draft connection agreement, bank guarantee proforma, and a transmission agreement with POWERGRID for dedicated systems.
Read with this
The regulation
Amendments and corrections
- Dated 3 Sep 2010Inter-State Connectivity, Long-term Access and Medium-term Open Access Regulations, 2009 — Amendment, 2010
- Dated 21 Mar 2012Connectivity, LTA and MTOA in inter-State Transmission Regulations, 2009 — Second Amendment, 2012
- Dated 26 Mar 2013Connectivity, LTA and MTOA (Third Amendment) Regulations, 2013
- Dated 12 Aug 2014Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Fourth Amendment, 2014
- Dated 15 May 2015Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2015
- Dated 17 Feb 2017Inter-State Connectivity, LTA and MTOA Regulations, 2009 — Sixth Amendment, 2017
- Dated 17 Feb 2017Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Sixth Amendment, 2017
- Dated 9 Jan 2019Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Seventh Amendment) Regulations, 2019
- Dated 5 Aug 2019Corrigendum 2 to Notification dated 9 January 2019
Commencement notices and reasons
- Dated 7 Aug 2009Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Order directing gazette publication
- Dated 30 Oct 2009Connectivity, Long-Term Access and Medium-Term Open Access to the Inter-State Transmission Regulations, 2009 — Statement of Reasons
- Dated 21 Mar 2012Connectivity, LTA and MTOA Regulations, 2009 — Second Amendment, 2012 — Statement of Reasons
- Dated 6 May 2015Connectivity Regulations, 2009 — Fourth Amendment, 2014 — Statement of Reasons
- Dated 15 May 2015Connectivity, LTA and MTOA Regulations, 2009 and Regulatory Approval Regulations, 2010 — Fifth Amendment, 2015 — Statement of Reasons
- Dated 28 Mar 2018Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Sixth Amendment) Regulations, 2017 — Statement of Reasons
- Dated 9 Jan 2019Connectivity Regulations, 2018 — Seventh Amendment — Statement of Reasons
- Date not statedConnectivity, LTA and MTOA (Third Amendment) Regulations, 2013 — Statement of Reasons
Procedures and orders made under it
- Dated 15 May 2018Approval of Detailed Procedure for Grant of Connectivity to RE Projects to ISTS, 2018 — Order
- Dated 20 Feb 2021Revised Procedure for Grant of Connectivity to Renewable Projects to the Inter-State Transmission System — Order, 2021
- Date not statedDetailed Procedure for Grant of Connectivity to Renewable Projects to ISTS
- Date not statedRevised Procedure for Grant of Connectivity to Projects based on Renewable Sources to ISTS
Other copies of these documents (7)
- Dated 7 Jul 2009Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009
- Dated 3 Sep 2010Connectivity, Long-term Access and Medium-term Open Access in Inter-State Transmission Regulations, 2009 — Amendment, 2010
- Dated 21 Mar 2012Grant of Connectivity, Long-term Access and Medium-term Open Access (Second Amendment) Regulations, 2012
- Dated 26 Mar 2013Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Third Amendment) Regulations, 2013
- Dated 12 Aug 2014Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2014
- Dated 15 May 2015Connectivity, LTA and MTOA (Fifth Amendment) Regulations, 2015
- Dated 9 Jan 2019Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Seventh Amendment) Regulations, 2019
Proposed changes (drafts with no final yet)
- Dated 16 Apr 2015Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Fourth Amendment, 2015 — Draft
- Released with the notice dated 16 Apr 2015Explanatory memorandum: Explanatory Memorandum — Connectivity/LTA/MTOA (Fourth Amendment) and CTU Regulatory Approval (First Amendment) Regulations, 2015
- Dated 16 Apr 2015Public notice: Public Notice — Draft Connectivity, Long-term Access and Medium-term Open Access (Fourth Amendment) and CTU Regulatory Approval (First Amendment) Regulations, 2015
- Released with the notice dated 11 Apr 2018Draft Procedure for Grant of Connectivity to Renewable Projects to ISTS
- Dated 11 Apr 2018Public notice: Public Notice on Draft Procedure for Grant of Connectivity to Renewable Energy Projects, 2018
- Released with the notice dated 24 Jul 2020Detailed Procedure for Grant of Connectivity to Renewable Projects to ISTS
- Dated 24 Jul 2020Public notice: Draft Amendment to Detailed Procedure for Renewable Connectivity to Inter-State Transmission — Public Notice, 2020
Earlier drafts
- Dated 7 Jul 2009Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Consolidated
- Released with the draft dated 7 Jul 2009Explanatory memorandum: Connectivity, LTA and MTOA Seventh Amendment Regulations, 2018 — Explanatory Memorandum — Draft
- Dated 9 Aug 2018Public notice: Public Notice — Draft Connectivity, Long-term Access and Medium-term Open Access (Seventh Amendment) Regulations, 2018
- Dated 5 Sep 2018Notice extending the date for comments: Public Notice — Extension of comments deadline on Draft Connectivity, LTA and MTOA (Seventh Amendment) Regulations, 2018
- Dated 22 Feb 2013Connectivity, LTA and MTOA (Third Amendment) Regulations, 2013 — Draft
- Dated 22 Feb 2013Public notice: Connectivity, LTA and MTOA in inter-State Transmission (Third Amendment) Regulations, 2013 — Draft — Public Notice
- Released with the notice dated 22 Feb 2013Explanatory memorandum: Connectivity, LTA and MTOA (Third Amendment) Regulations, 2013 — Explanatory Memorandum — Draft
- Dated 18 Feb 2014Inter-State Transmission Connectivity, Long-term Access and Medium-term Open Access (Fourth Amendment) Regulations, 2014 — Draft
- Released with the draft dated 18 Feb 2014File: Start-up Power for New Generating Stations Procedure, 2014
- Dated 20 Feb 2014Explanatory memorandum: Explanatory Memorandum to the Connectivity Regulations, 2009 Amendment, 2014
- Dated 24 Feb 2014Public notice: Connectivity, Long-term Access and Medium-term Open Access (Fourth Amendment) Regulations, 2014 — Draft
- Dated 28 Oct 2016Grant of Connectivity, Long-term Access and Medium-term Open Access (Sixth Amendment) Regulations, 2016 — Draft
- Released with the draft dated 28 Oct 2016Explanatory memorandum: Explanatory Memorandum to draft Connectivity, LTA and MTOA (Sixth Amendment) Regulations, 2015 and Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2016 — Draft
- Dated 16 Nov 2016Notice extending the date for comments: Public Notice — Extension of comment deadline on draft Connectivity, LTA and MTOA (Sixth Amendment) and Sharing of Inter-State Transmission Charges & Losses (Fifth Amendment) Regulations, 2016
- Dated 9 Aug 2018Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Seventh Amendment, 2018 — Draft
4 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.