Connectivity, LTA and MTOA Regulations, 2009 — Second Amendment, 2012 — Statement of Reasons

Central Electricity Regulatory Commission (Grant of Connectivity, Long-Term Access and Medium-Term Open Access in Inter-State Transmission and related matters) (Second Amendment) Regulations, 2012.

Statement of reasonsDated 21 Mar 2012

Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Central Electricity Regulatory Commission's Statement of Reasons dated 21 March 2012 for the Second Amendment to the 2009 Connectivity, Long-Term Access and Medium-Term Open Access Regulations (p1). It records the consultation process and explains the Commission's final decisions, then directs that the amendment be finalized and notified (p43–44). It is not the notified regulation itself; the operative text appears as quoted clauses within the reasons.

Pages 1–3 set out the consultation history: the draft amendment was published on 2 June 2011, supplementary draft amendments on 25 July 2011, about 17 stakeholders commented, and a public hearing was held on 12 October 2011 (p1–2). Annexure-I lists the stakeholders (p2).

Pages 3–23 deal with Regulation 8(7) on infirm power. The draft proposed a three-month limit and allowed sale through bilateral arrangements. The final decision allows injection during testing before COD for up to six months from first synchronization with prior RLDC permission, permits extension on application two months in advance in exceptional circumstances, treats infirm power as Unscheduled Interchange under the UI Regulations, and deletes the proposed scheduling/bilateral sale provision (pp9–14, 16, 22–23). The UI cap rates are moved to the UI Regulations Second Amendment 2012 (pp20–22).

Pages 23–36 deal with Regulation 8(8) on dedicated transmission lines. The final text allows phased construction by CTU or the transmission licensee after the generator has paid advances for main plant packages, subject to a minimum of 10% of the contract value, and makes transmission charges payable even if the generation project is delayed or abandoned (pp29, 36). The Commission rejects CTU's proposed pre-requisites for grant of connectivity, directs CTU to submit a revised detailed procedure, and clarifies PoC treatment of dedicated lines built through coordinated planning (pp26–36).

Pages 36–40 cover Regulation 12. Phased construction for LTA through coordinated planning is retained; the proposed offsetting of STOA/MTOA charges against LTA transmission charges is referred to the Sharing Regulations; and the proposed three-year deadline for CTU to build the last leg is dropped (pp37–40).

Pages 40–44 cover PPA termination and LTA surrender. New Regulation 15A requires intimation of PPA termination within two weeks and allows CTU or the transmission licensee to seek surrender of LTA unused for over one year, with liability under Regulation 18; new Regulation 16A lets the nodal agency inform RLDC/SLDC to process STOA on vacated capacity (pp41–44).

Standard name
Connectivity and GNA Regulations
Primary topics
Connectivity and GNA, Open access, Power procurement and PPAs

Read with this

Other copies of these documents (7)

Earlier drafts

4 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document