CERC · Central Electricity Regulatory Commission
Connectivity, LTA and MTOA in inter-State Transmission Regulations, 2009 — Second Amendment, 2012
Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters)( Second Amendment) Regulations, 2012
AmendmentDated 21 Mar 2012No.–L-1/(3)/2009-CERC dated 21st March, 2012
Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022
See that regulation for the date it took effect and for anything it keeps in force.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Central Electricity Regulatory Commission's Second Amendment to the 2009 regulations governing grant of connectivity, long-term access (LTA) and medium-term open access (MTOA) in inter-State transmission. It is a short, five-clause amending instrument dated 21 March 2012 (p1) and takes effect from the date of publication in the Official Gazette — a date not printed in this text (p1).
Clause 2 substitutes Regulation 8(7) of the principal regulations, restating the regime under which a generating unit, including a captive generating plant, may inject infirm power during testing and full-load testing before COD — subject to prior permission of the concerned RLDC, a time limit running from first synchronization, a Commission-granted extension on advance application, grid-security provisos, an onus on the generator to prove testing purpose, and treatment of the injected power as Unscheduled Interchange paid per the CERC UI Regulations, 2009 (p1–3). It also adds two provisos to Regulation 8(8) on phased construction of dedicated transmission lines, tying phases to capacity likely to be commissioned and to advance payments on main plant or EPC packages, and making transmission charges payable even if the project is delayed or abandoned (p3).
Clause 3 rewrites the third proviso to Regulation 12(1) on phased construction of the transmission system on a similar basis, and inserts a proviso requiring a generator that has firmed up beneficiaries through signing long-term PPAs to notify the nodal agency with a copy of the PPA (p3–4). Clause 4 adds a new Regulation 15A obliging an LTA customer to intimate termination of its PPA to the nodal agency within two weeks, empowering CTU/transmission licensee to seek surrender of LTA where access is mutually terminated or unused for over a year and another project would be stranded, and preserving liability for transmission charges under Regulation 18; the nodal agency may then consider MTOA applications on the freed corridor (p4–6). Clause 5 adds Regulation 16A, routing freed capacity to RLDC/SLDC for processing short-term open access requests under the 2008 Open Access regulations until LTA or MTOA is granted to another applicant (p6–7). A closing Note records the gazette details of the principal regulations and the first amendment (p7).
Read with this
The regulation
Amendments and corrections
- Dated 3 Sep 2010Inter-State Connectivity, Long-term Access and Medium-term Open Access Regulations, 2009 — Amendment, 2010
- Dated 26 Mar 2013Connectivity, LTA and MTOA (Third Amendment) Regulations, 2013
- Dated 12 Aug 2014Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Fourth Amendment, 2014
- Dated 15 May 2015Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2015
- Dated 17 Feb 2017Inter-State Connectivity, LTA and MTOA Regulations, 2009 — Sixth Amendment, 2017
- Dated 17 Feb 2017Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Sixth Amendment, 2017
- Dated 9 Jan 2019Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Seventh Amendment) Regulations, 2019
- Dated 5 Aug 2019Corrigendum 2 to Notification dated 9 January 2019
Commencement notices and reasons
- Dated 7 Aug 2009Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Order directing gazette publication
- Dated 30 Oct 2009Connectivity, Long-Term Access and Medium-Term Open Access to the Inter-State Transmission Regulations, 2009 — Statement of Reasons
- Dated 21 Mar 2012Connectivity, LTA and MTOA Regulations, 2009 — Second Amendment, 2012 — Statement of Reasons
- Dated 6 May 2015Connectivity Regulations, 2009 — Fourth Amendment, 2014 — Statement of Reasons
- Dated 15 May 2015Connectivity, LTA and MTOA Regulations, 2009 and Regulatory Approval Regulations, 2010 — Fifth Amendment, 2015 — Statement of Reasons
- Dated 28 Mar 2018Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Sixth Amendment) Regulations, 2017 — Statement of Reasons
- Dated 9 Jan 2019Connectivity Regulations, 2018 — Seventh Amendment — Statement of Reasons
- Date not statedConnectivity, LTA and MTOA (Third Amendment) Regulations, 2013 — Statement of Reasons
Procedures and orders made under it
- Dated 31 Dec 2009Procedure for Making Application for Grant of Connectivity in ISTS, 2009
- Dated 15 May 2018Approval of Detailed Procedure for Grant of Connectivity to RE Projects to ISTS, 2018 — Order
- Dated 20 Feb 2021Revised Procedure for Grant of Connectivity to Renewable Projects to the Inter-State Transmission System — Order, 2021
- Date not statedDetailed Procedure for Grant of Connectivity to Renewable Projects to ISTS
- Date not statedRevised Procedure for Grant of Connectivity to Projects based on Renewable Sources to ISTS
Other copies of these documents (7)
- Dated 7 Jul 2009Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009
- Dated 3 Sep 2010Connectivity, Long-term Access and Medium-term Open Access in Inter-State Transmission Regulations, 2009 — Amendment, 2010
- Dated 21 Mar 2012Grant of Connectivity, Long-term Access and Medium-term Open Access (Second Amendment) Regulations, 2012
- Dated 26 Mar 2013Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Third Amendment) Regulations, 2013
- Dated 12 Aug 2014Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2014
- Dated 15 May 2015Connectivity, LTA and MTOA (Fifth Amendment) Regulations, 2015
- Dated 9 Jan 2019Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Seventh Amendment) Regulations, 2019
Proposed changes (drafts with no final yet)
- Dated 16 Apr 2015Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Fourth Amendment, 2015 — Draft
- Released with the notice dated 16 Apr 2015Explanatory memorandum: Explanatory Memorandum — Connectivity/LTA/MTOA (Fourth Amendment) and CTU Regulatory Approval (First Amendment) Regulations, 2015
- Dated 16 Apr 2015Public notice: Public Notice — Draft Connectivity, Long-term Access and Medium-term Open Access (Fourth Amendment) and CTU Regulatory Approval (First Amendment) Regulations, 2015
- Released with the notice dated 11 Apr 2018Draft Procedure for Grant of Connectivity to Renewable Projects to ISTS
- Dated 11 Apr 2018Public notice: Public Notice on Draft Procedure for Grant of Connectivity to Renewable Energy Projects, 2018
- Released with the notice dated 24 Jul 2020Detailed Procedure for Grant of Connectivity to Renewable Projects to ISTS
- Dated 24 Jul 2020Public notice: Draft Amendment to Detailed Procedure for Renewable Connectivity to Inter-State Transmission — Public Notice, 2020
Earlier drafts
- Dated 7 Jul 2009Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Consolidated
- Released with the draft dated 7 Jul 2009Explanatory memorandum: Connectivity, LTA and MTOA Seventh Amendment Regulations, 2018 — Explanatory Memorandum — Draft
- Dated 9 Aug 2018Public notice: Public Notice — Draft Connectivity, Long-term Access and Medium-term Open Access (Seventh Amendment) Regulations, 2018
- Dated 5 Sep 2018Notice extending the date for comments: Public Notice — Extension of comments deadline on Draft Connectivity, LTA and MTOA (Seventh Amendment) Regulations, 2018
- Dated 22 Feb 2013Connectivity, LTA and MTOA (Third Amendment) Regulations, 2013 — Draft
- Dated 22 Feb 2013Public notice: Connectivity, LTA and MTOA in inter-State Transmission (Third Amendment) Regulations, 2013 — Draft — Public Notice
- Released with the notice dated 22 Feb 2013Explanatory memorandum: Connectivity, LTA and MTOA (Third Amendment) Regulations, 2013 — Explanatory Memorandum — Draft
- Dated 18 Feb 2014Inter-State Transmission Connectivity, Long-term Access and Medium-term Open Access (Fourth Amendment) Regulations, 2014 — Draft
- Released with the draft dated 18 Feb 2014File: Start-up Power for New Generating Stations Procedure, 2014
- Dated 20 Feb 2014Explanatory memorandum: Explanatory Memorandum to the Connectivity Regulations, 2009 Amendment, 2014
- Dated 24 Feb 2014Public notice: Connectivity, Long-term Access and Medium-term Open Access (Fourth Amendment) Regulations, 2014 — Draft
- Dated 28 Oct 2016Grant of Connectivity, Long-term Access and Medium-term Open Access (Sixth Amendment) Regulations, 2016 — Draft
- Released with the draft dated 28 Oct 2016Explanatory memorandum: Explanatory Memorandum to draft Connectivity, LTA and MTOA (Sixth Amendment) Regulations, 2015 and Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2016 — Draft
- Dated 16 Nov 2016Notice extending the date for comments: Public Notice — Extension of comment deadline on draft Connectivity, LTA and MTOA (Sixth Amendment) and Sharing of Inter-State Transmission Charges & Losses (Fifth Amendment) Regulations, 2016
- Dated 9 Aug 2018Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Seventh Amendment, 2018 — Draft
4 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.