Connectivity, LTA and MTOA (Third Amendment) Regulations, 2013

Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) (Third Amendment) Regulations, 2013

AmendmentDated 26 Mar 2013No.L-1(3)/2009-CERC.- dated 26th of March 2013

Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a two-page CERC notification that amends, for the third time, the 2009 regulations governing grant of connectivity, long-term access and medium-term open access in inter-State transmission (p1). The amendment does two things.

First, it creates a new class of applicant under Regulation 2 by adding sub-clause (e): a renewable energy generating station of 5 MW and above but less than 50 MW, developed by a generating company inside its own existing generating station, seeking connectivity to the existing connection point through that station's electrical system (p1). This lets such a station ride on the host station's interconnection rather than seeking its own.

Second, it adds a proviso to Regulation 8: CTU will consider such an application only if the existing generating station agrees to act as "Principal Generator" on behalf of the embedded renewable station(s), formalised in a written agreement under which the host takes on all operational and commercial responsibilities — grid code compliance, grid security, scheduling and despatch, and collection and payment or adjustment of transmission charges, UI charges, congestion and other charges — with a copy filed with CTU along with the application and with the concerned RLDC (p2).

The regulations come into force from the date of Gazette publication; the Gazette date itself is not printed (p1). A closing Note records the Gazette references for the principal regulations and the first two amendments (p2).

Standard name
Connectivity and GNA Regulations, Open Access Regulations
Primary topics
Connectivity and GNA, Open access

Read with this

Other copies of these documents (7)

Earlier drafts

4 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.