Grant of Connectivity, Long-term Access and Medium-term Open Access (Second Amendment) Regulations, 2012

Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) (Second Amendment) Regulations, 2012

Amendment · Gazette copyDated 21 Mar 2012Published in the Gazette 22 Mar 2012No.-L-1/ (3) /2009-CERC. dated New Delhi, the 21st March, 2012

Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

The Gazette copy of the Connectivity, LTA and MTOA in inter-State Transmission Regulations, 2009 — Second Amendment, 2012.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Second Amendment, made in 2012, to CERC's 2009 regulations on grant of connectivity, long-term access (LTA) and medium-term open access (MTOA) in inter-State transmission. It was issued by the Central Electricity Regulatory Commission on 21 March 2012 under notification No. L-1/(3)/2009-CERC and published in the Gazette of India Extraordinary, Part III, Section 4, on 22 March 2012 (p1, p5, p11). It takes effect from the Gazette publication date, so there is no retrospective or deferred operation (p5).

The instrument is purely amending — it creates no standalone entitlements and works by substituting or inserting provisions in the CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 ("the Principal Regulations"). Five clauses follow the short title.

Clause 2 substitutes Regulation 8(7), setting out when a unit of a generating station, including a captive generating plant, that has been granted connectivity may inject infirm power during testing before COD: RLDC prior permission, a capped testing window from first synchronisation, a Commission power to extend it in exceptional circumstances on advance application, a grid-security condition on the RLDC, and treatment of such power as Unscheduled Interchange with payment under the 2009 UI regulations (p5–7). Two provisos are added to Regulation 8(8) letting the CTU or transmission licensee build a dedicated transmission line in phases, against evidence that the generator has already paid advances on main plant packages, and making transmission charges payable even if the project is delayed or abandoned (p7).

Clause 3 substitutes the third proviso to Regulation 12(1) to allow phased augmentation of the transmission system on the same advance-payment basis, and inserts a further proviso requiring a generator that has firmed up beneficiaries through long-term PPAs to notify the nodal agency along with a copy of the PPA (p7–8).

Clause 4 inserts Regulation 15A, obliging a long-term access customer to intimate termination of its PPA to the nodal agency within a fixed short deadline; it also lets the CTU or transmission licensee seek surrender of LTA on mutual termination or prolonged non-utilisation, permits them to approach the Commission for directions, preserves the customer's liability for transmission charges under Regulation 18, and allows the nodal agency to consider MTOA applications over the freed corridor (p8–10).

Clause 5 inserts Regulation 16A: on such termination or surrender the nodal agency is to inform RLDC and SLDC to consider the remaining capacity for short-term open access applications until LTA or MTOA is granted to someone else (p10–11). The closing Note records when the Principal Regulations and their First Amendment were notified (p11).

Standard name
Connectivity and GNA Regulations
Primary topics
Connectivity and GNA, Open access, Transmission tariff

Read with this

Other copies of these documents (6)

Earlier drafts

4 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.