CERC · Central Electricity Regulatory Commission

Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Seventh Amendment) Regulations, 2019

Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) (Seventh Amendment) Regulations, 2019

AmendmentDated 9 Jan 2019No.–L-1/(3)/2009-CERC dated 9 thJanuary, 2019

Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Seventh Amendment to CERC's 2009 connectivity and open-access regulations, signed by the Secretary on 9 January 2019 and to come into force on Gazette publication (the Gazette date is not printed) (p1), re-draws the entry rules for the inter-State transmission system. Clause 2 (pp1–4) restates who is an eligible applicant under Regulation 2: it fixes capacity thresholds distinguishing non-renewable generating stations and captive plants, renewable energy generating stations, and hydro stations of a middle capacity band; creates a "lead generator" route for clusters of small hydro, standalone storage and renewable stations that individually fall below the threshold but aggregate above it; adds a route for renewable capacity built within or alongside an existing generating station or renewable power park; and brings in renewable power park developers, Renewable Energy Implementing Agencies, and standalone storage projects. New definitions are inserted for Renewable Energy Implementing Agency, Renewable Energy Generating Station, Renewable Hybrid Generating Station, Renewable Hybrid Power Park, Renewable Power Park Developers and Storage (pp3–4).

Clause 3 (pp4–5) exempts transmission licensees from applying for connectivity and inserts a new Regulation 5A prescribing online application, date-stamping, monthly cut-off for deemed receipt, deficiency intimation and rectification windows, closure with part-forfeiture of application fees, and return of bank guarantees. Clause 4 (pp5–9) amends Regulation 8: it sets the material-change threshold that forces a fresh application, allows an existing grantee to add capacity at the same connectivity with CTU approval, devotes a clause to storage projects applying on maximum injection or drawal, introduces two-stage (Stage-I/Stage-II) connectivity for renewable, storage and implementing-agency applicants with the 2018 renewable connectivity procedure deemed issued under the regulations, provides for transfer of Stage-I connectivity and LTA from an implementing agency to the selected generators, and allocates development, ownership and length limits of dedicated transmission lines as well as cancellation and re-allocation of unused bays. A new Regulation 8A (pp8–9) states a general bar on transferring, assigning or pledging connectivity or LTA, with carve-outs for implementing agencies and for parent/subsidiary transfers after commercial operation.

Clauses 5–11 (pp9–11) make consequential and substantive changes: terminology in Regulation 9; a renewable-energy exception and a threshold cross-reference in Regulation 12, plus a new clause providing that Stage-II connectivity is not a pre-requisite for applying for LTA; deletion of the first proviso and clause (3) of Regulation 13; wholesale substitution of Regulation 15 (long-term access agreements, including tripartite agreements and agreement contents) and of Regulation 21(1) (medium-term open access agreements); deletion of Regulation 27(2)(c); and deletion of Regulation 29. The closing Note (p11) lists the Principal Regulations and each earlier amendment with its Gazette date.

Standard name
Connectivity and GNA Regulations, Open Access Regulations
Primary topics
Connectivity and GNA, Open access, Energy storage deployment

Read with this

Other copies of these documents (7)

Earlier drafts

4 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.