CERC · Central Electricity Regulatory Commission
Connectivity, LTA and MTOA Regulations, 2009 and Regulatory Approval Regulations, 2010 — Fifth Amendment, 2015 — Statement of Reasons
Amendments to Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 and Central Electricity Regulatory Commission (Grant of Regulatory Approval for execution of Inter-State Transmission Scheme to Central Transmission Utility) Regulations, 2010
Statement of reasonsDated 15 May 2015
Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022
See that regulation for the date it took effect and for anything it keeps in force.
The commission's reasons for the Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 or one of its amendments.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Commission's reasoned decision on two linked sets of draft amendments published for comment on 16 April 2015 (p2), explaining why they were adopted and in what modified form. It responds to the Government of India's solar park programme — MNRE's letter of 12 December 2014 setting out a framework for solar parks and for pooling/evacuation infrastructure (p1) — and to comments from PGCIL, NTPC, CEA, MNRE, APP, InWEA, Saurya Urja Company of Rajasthan and an individual (p2, pp4–5, pp8–9).
The core decision (pp3–7) makes a Solar Power Park Developer (SPPD) an eligible entity to apply for connectivity and long-term access to inter-State transmission, with the draft's word "designated" changed to "authorised" by the Central Government. The Commission declines to open eligibility generally to State-designated developers or to wind park developers, and clarifies that the SPPD acts as an agent of the generating companies.
A second amendment (pp7–11) would have made CTU's consideration of an SPPD application conditional on the developer bearing all operational and commercial responsibilities; that proviso is narrowed to authorisation for infrastructural activities, because scheduling, metering, energy accounting, DSM and congestion charges are referred to a detailed procedure to be prepared by NLDC within one month, followed by an IEGC amendment (p10).
The SoR then settles three further questions: the transmission system inside a solar park is a dedicated transmission line and needs no transmission licence (pp11–13); transmission charges for delay in commissioning stay payable by the generators/SPPD despite the solar exemption in the Sharing Regulations, which applies only after commercial operation (pp13–15); and SPPD's costs are to be borne by generators through their own agreements (pp15–16). It ends with the parallel amendment to the Regulatory Approval Regulations, 2010, allowing CTU to seek regulatory approval for an ISTS scheme tied to an authorised SPPD's LTA application (pp16–17).
Read with this
Read with this: Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009
The regulation
Amendments and corrections
- Dated 3 Sep 2010Inter-State Connectivity, Long-term Access and Medium-term Open Access Regulations, 2009 — Amendment, 2010
- Dated 21 Mar 2012Connectivity, LTA and MTOA in inter-State Transmission Regulations, 2009 — Second Amendment, 2012
- Dated 26 Mar 2013Connectivity, LTA and MTOA (Third Amendment) Regulations, 2013
- Dated 12 Aug 2014Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Fourth Amendment, 2014
- Dated 15 May 2015Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2015
- Dated 17 Feb 2017Inter-State Connectivity, LTA and MTOA Regulations, 2009 — Sixth Amendment, 2017
- Dated 17 Feb 2017Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Sixth Amendment, 2017
- Dated 9 Jan 2019Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Seventh Amendment) Regulations, 2019
- Dated 5 Aug 2019Corrigendum 2 to Notification dated 9 January 2019
Commencement notices and reasons
- Dated 7 Aug 2009Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Order directing gazette publication
- Dated 30 Oct 2009Connectivity, Long-Term Access and Medium-Term Open Access to the Inter-State Transmission Regulations, 2009 — Statement of Reasons
- Dated 21 Mar 2012Connectivity, LTA and MTOA Regulations, 2009 — Second Amendment, 2012 — Statement of Reasons
- Dated 6 May 2015Connectivity Regulations, 2009 — Fourth Amendment, 2014 — Statement of Reasons
- Dated 28 Mar 2018Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Sixth Amendment) Regulations, 2017 — Statement of Reasons
- Dated 9 Jan 2019Connectivity Regulations, 2018 — Seventh Amendment — Statement of Reasons
- Date not statedConnectivity, LTA and MTOA (Third Amendment) Regulations, 2013 — Statement of Reasons
Procedures and orders made under it
- Dated 31 Dec 2009Procedure for Making Application for Grant of Connectivity in ISTS, 2009
- Dated 15 May 2018Approval of Detailed Procedure for Grant of Connectivity to RE Projects to ISTS, 2018 — Order
- Dated 20 Feb 2021Revised Procedure for Grant of Connectivity to Renewable Projects to the Inter-State Transmission System — Order, 2021
- Date not statedDetailed Procedure for Grant of Connectivity to Renewable Projects to ISTS
- Date not statedRevised Procedure for Grant of Connectivity to Projects based on Renewable Sources to ISTS
Other copies of these documents (7)
- Dated 7 Jul 2009Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009
- Dated 3 Sep 2010Connectivity, Long-term Access and Medium-term Open Access in Inter-State Transmission Regulations, 2009 — Amendment, 2010
- Dated 21 Mar 2012Grant of Connectivity, Long-term Access and Medium-term Open Access (Second Amendment) Regulations, 2012
- Dated 26 Mar 2013Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Third Amendment) Regulations, 2013
- Dated 12 Aug 2014Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2014
- Dated 15 May 2015Connectivity, LTA and MTOA (Fifth Amendment) Regulations, 2015
- Dated 9 Jan 2019Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Seventh Amendment) Regulations, 2019
Proposed changes (drafts with no final yet)
- Dated 16 Apr 2015Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Fourth Amendment, 2015 — Draft
- Released with the notice dated 16 Apr 2015Explanatory memorandum: Explanatory Memorandum — Connectivity/LTA/MTOA (Fourth Amendment) and CTU Regulatory Approval (First Amendment) Regulations, 2015
- Dated 16 Apr 2015Public notice: Public Notice — Draft Connectivity, Long-term Access and Medium-term Open Access (Fourth Amendment) and CTU Regulatory Approval (First Amendment) Regulations, 2015
- Released with the notice dated 11 Apr 2018Draft Procedure for Grant of Connectivity to Renewable Projects to ISTS
- Dated 11 Apr 2018Public notice: Public Notice on Draft Procedure for Grant of Connectivity to Renewable Energy Projects, 2018
- Released with the notice dated 24 Jul 2020Detailed Procedure for Grant of Connectivity to Renewable Projects to ISTS
- Dated 24 Jul 2020Public notice: Draft Amendment to Detailed Procedure for Renewable Connectivity to Inter-State Transmission — Public Notice, 2020
Earlier drafts
- Dated 7 Jul 2009Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Consolidated
- Released with the draft dated 7 Jul 2009Explanatory memorandum: Connectivity, LTA and MTOA Seventh Amendment Regulations, 2018 — Explanatory Memorandum — Draft
- Dated 9 Aug 2018Public notice: Public Notice — Draft Connectivity, Long-term Access and Medium-term Open Access (Seventh Amendment) Regulations, 2018
- Dated 5 Sep 2018Notice extending the date for comments: Public Notice — Extension of comments deadline on Draft Connectivity, LTA and MTOA (Seventh Amendment) Regulations, 2018
- Dated 22 Feb 2013Connectivity, LTA and MTOA (Third Amendment) Regulations, 2013 — Draft
- Dated 22 Feb 2013Public notice: Connectivity, LTA and MTOA in inter-State Transmission (Third Amendment) Regulations, 2013 — Draft — Public Notice
- Released with the notice dated 22 Feb 2013Explanatory memorandum: Connectivity, LTA and MTOA (Third Amendment) Regulations, 2013 — Explanatory Memorandum — Draft
- Dated 18 Feb 2014Inter-State Transmission Connectivity, Long-term Access and Medium-term Open Access (Fourth Amendment) Regulations, 2014 — Draft
- Released with the draft dated 18 Feb 2014File: Start-up Power for New Generating Stations Procedure, 2014
- Dated 20 Feb 2014Explanatory memorandum: Explanatory Memorandum to the Connectivity Regulations, 2009 Amendment, 2014
- Dated 24 Feb 2014Public notice: Connectivity, Long-term Access and Medium-term Open Access (Fourth Amendment) Regulations, 2014 — Draft
- Dated 28 Oct 2016Grant of Connectivity, Long-term Access and Medium-term Open Access (Sixth Amendment) Regulations, 2016 — Draft
- Released with the draft dated 28 Oct 2016Explanatory memorandum: Explanatory Memorandum to draft Connectivity, LTA and MTOA (Sixth Amendment) Regulations, 2015 and Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2016 — Draft
- Dated 16 Nov 2016Notice extending the date for comments: Public Notice — Extension of comment deadline on draft Connectivity, LTA and MTOA (Sixth Amendment) and Sharing of Inter-State Transmission Charges & Losses (Fifth Amendment) Regulations, 2016
- Dated 9 Aug 2018Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Seventh Amendment, 2018 — Draft
4 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.
It is also read with: Grant of Regulatory Approval for Execution of Inter-State Transmission Scheme to Central Transmission Utility Regulations, 2010
The commission's reasons for the Grant of Regulatory Approval for Execution of Inter-State Transmission Scheme to Central Transmission Utility Regulations, 2010 or one of its amendments.
The regulation
Amendments and corrections
Commencement notices and reasons
Other copies of these documents (1)
Proposed changes (drafts with no final yet)
- Released with the notice dated 16 Apr 2015Explanatory memorandum: Explanatory Memorandum — Connectivity/LTA/MTOA (Fourth Amendment) and CTU Regulatory Approval (First Amendment) Regulations, 2015
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.