Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009

Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009

RegulationDated 7 Aug 2009No.–L-1/(3)/2009-CERC dated 7th August 2009

Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The notification (p1) makes the CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 — the framework under which generators, captive plants, bulk consumers, traders and distribution licensees are connected to, and obtain rights to use, the inter-State transmission system. It is made under section 178 of the Electricity Act, 2003, and commencement is deferred: the regulations take effect on a date the Commission has yet to notify, and only after it has approved the Central Transmission Utility's "detailed procedure" (p1).

Chapters 1 and 2 (p1–7) define the key terms and eligibility thresholds, set the scope, name the CTU as nodal agency, and prescribe how applications are filed, the fee slabs by quantum of power and type of access, and the time limits for processing. Chapter 3 (p7–10) covers grant of connectivity: what an application must contain and when a fresh one is needed, interconnection studies under the CEA Technical Standards for Connectivity to the Grid Regulations, 2007, identification of the connection point, connection and tripartite agreements, the rule that connectivity alone confers no right to interchange power, testing/infirm power, and the dedicated-line obligation with its exemptions (p10).

Chapter 4 (p11–13) sets the criteria for long-term access and medium-term open access, the first-come-first-served priority rules (including monthly concurrency and the requirement of SLDC concurrence for intra-State entities), and interface metering responsibility. Chapter 5 (p13–21) governs long-term access — application content, the per-MW bank guarantee, system studies, competitive-bidding route for augmentation, communication of estimated transmission charges, the long-term access agreement, renewal on written request, and compensation for relinquishment of rights via stranded transmission capacity, which is recycled to other customers. Chapter 6 (p21–23) does the same for medium-term open access: the application window, the bar on augmentation solely for MTOA, grant and agreement, dedicated line at the customer's risk, no renewal preference, and exit on notice.

Chapter 7 (p24–30) sets the operating conditions: curtailment priority across customer classes, recovery of transmission charges, the contents of the detailed procedure the CTU must submit for approval, RLDC/SLDC fees and charges, day-ahead scheduling and Unscheduled Interchange accounting (with separate treatment for intra-State entities), transmission losses and dispute redressal before the Commission. Chapter 8 (p30–31) requires the nodal agency to publish applications, grants and refusals on its website; Chapter 9 (p32) repeals specified clauses of the 2004 inter-State open access regulations, with savings for long-term access already granted.

Standard name
Connectivity and GNA Regulations, Open Access Regulations
Primary topics
Open access, Connectivity and GNA, Transmission tariff

Read with this

Other copies of these documents (7)

Earlier drafts

4 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.