Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009

Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009

Gazette copyDated 7 Jul 2009Published in the Gazette 10 Aug 2009No. L-1(3)/2009-CERC dated New Delhi, the 7th July, 2009

Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

A Gazette copy of the Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 or of one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's principal regulation for granting connectivity to the inter-State transmission system and for long-term access (LTA) and medium-term open access (MTOA) over it. It was notified on 7 July 2009 (p13) and printed in the Gazette of India, Extraordinary, on 10 August 2009 (p1), and is made under section 178 of the Electricity Act, 2003 (p13).

Critically, it does not start operating on its own. Regulation 1(2) leaves commencement to a date the Commission is to notify, and that date must fall after the Commission approves the Central Transmission Utility's "detailed procedure" (p13). Much of the operational detail — application forms, proformas for the connection, LTA and MTOA agreements, payment security and bank guarantee mechanics, construction timelines — is therefore deferred to that CTU procedure, which the CTU must submit within 60 days of gazette notification, after publishing a draft for one month's public comment (p20–21).

Chapter 2 makes the CTU the nodal agency for all applications and sets who must apply, the application fees (a table keyed to quantum of power and to the type of access) and the outer time limits for processing — 60 days for connectivity, 120 or 180 days for long-term access depending on whether augmentation is needed, and 40 days for medium-term open access (p14–15). Chapter 3 governs connectivity: application contents, the inter-connection study under CEA's 2007 technical standards, connection and tripartite agreements, testing and injection of infirm power before commercial operation, and when an applicant must build a dedicated line (p15–16).

Chapters 4 to 6 set the access regime itself: criteria (long-term access measured against CEA augmentation plans; medium-term open access only where the existing or under-execution system can carry the flow, with no augmentation solely for MTOA), first-come-first-served priority within a month, SLDC concurrence for intra-State applicants, interface meters, the long-term access application and bank guarantee, system studies, the access agreement, renewal, and relinquishment with compensation for stranded transmission capacity on a net-present-value basis (p16–19). For medium-term open access the regulation fixes a window for the start date, lets the CTU grant a shorter period, and gives a 30-day exit (p19–20).

Chapter 7 sets conditions: curtailment order (short-term first, then medium-term, then long-term, pro rata within a class), transmission charges and SLDC/RLDC fees, routing of payments, day-ahead scheduling and unscheduled-interchange accounting, transmission losses and dispute resolution by the Commission (p20–22). Chapter 8 requires a standing CTU web page listing applications and grants; Chapter 9 repeals identified provisions of the 2004 Open Access Regulations while preserving long-term access already granted until its term expires (p22).

Standard name
Open Access Regulations, Connectivity and GNA Regulations
Primary topics
Open access, Connectivity and GNA, Network planning and investment

Read with this

Other copies of these documents (6)

Earlier drafts

4 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.