Explanatory Memorandum — Connectivity/LTA/MTOA (Fourth Amendment) and CTU Regulatory Approval (First Amendment) Regulations, 2015

Explanatory Memorandum to: Draft Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) (Fourth Amendment) Regulations, 2015 and Draft Central Electricity Regulatory Commission (Grant of Regulatory Approval for execution of Inter-State Transmission Scheme to Central Transmission Utility) (First Amendment) Regulations, 2015

Explanatory memorandum to a draftReleased with the notice dated 16 Apr 2015

Draft

Voltaic holds no final regulation made from this draft.

Explanatory memorandum to the Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Fourth Amendment, 2015 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's explanatory memorandum introducing two proposed amendments: the Fourth Amendment to the Connectivity/LTA/MTOA Regulations, 2015, and the First Amendment to the CTU Regulatory Approval Regulations, 2015 (p1). It is not the amendment text; it sets out the policy background and rationale for treating Solar Power Park Developers as eligible for connectivity and long-term access to inter-State transmission (p1–2).

The background explains MNRE's plan for solar parks — concentrated, infrastructure-ready zones for solar generation projects — and reproduces MNRE's letter of 12 December 2014. That framework envisages at least 25 solar parks, each exceeding 500 MW, targeting over 20,000 MW over 2014-15 to 2018-19 (p1). The reproduced extract allocates evacuation responsibilities: project developers connect plots to pooling stations; the designated nodal agency builds pooling stations and transmission to a 220 kV/400 kV substation; CTU or STU builds the nearby substation after technical and commercial procedures under CERC/State Commission regulations (p1–2). If a State Government buys over 50% of the park's generation, preference goes to STU; otherwise CTU may build a 400 kV or larger substation, with Power Grid potentially preparing a separate project funded from NCEF/external/Green Corridor funds, planned so solar wheeling charges are nil or affordable (p2). Implementing agencies must intimate CTU and CEA at least six months in advance (p2).

CERC then states that existing regulations do not treat such a developer as eligible for connectivity and LTA. It proposes to make the Solar Power Park Developer eligible. Such a developer is described as a company registered under the Companies Act, 2013 and designated by the Central Government to act for solar power generators on connectivity and LTA to the inter-State transmission system (p2). CERC also proposes to amend the 2010 CTU Regulatory Approval Regulations so that CTU-executed transmission schemes for solar park development are eligible for regulatory approval (p2). No commencement date or operative clause text is given.

Standard name
Connectivity and GNA Regulations
Primary topics
Connectivity and GNA, Open access, Network planning and investment

Read with this

Read with this: Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009

Other copies of these documents (7)

Earlier drafts

4 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document