Connectivity, LTA and MTOA (Third Amendment) Regulations, 2013 — Statement of Reasons

Central Electricity Regulatory Commission (Grant of Connectivity, Longterm Access and Medium-term Open Access in inter-State Transmission and related matters) (Third Amendment) Regulations, 2013

Statement of reasonsDate not stated

Replaced by Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's Statement of Reason explaining why it amended its 2009 Connectivity Regulations a third time, to let renewable generation be built inside, or alongside the facilities of, an existing generating station already connected to the inter-State transmission system and share that station's connection. Pages 1–2 set the background: the 2009 regulations (in force from 1.1.2010), the September 2010 amendment that cut the renewables threshold from 250 MW to 50 MW, and the proposal — circulated for comment by 15.03.2013 — to allow renewable stations of 1 MW and above at the existing ISTS connection point.

The bulk of the document (pp2–10) is the Commission's paragraph-by-paragraph response to comments from NTPC, POSOCO, CTU, CEA and M/s Transtech Green Power Pvt. Ltd. Under Connectivity and Metering (pp2–6) the Commission accepts that small renewable capacity should be integrated at the nearest available voltage level within the plant rather than stepped up to EHV, that it must not be connected to the state transmission system, and that renewable output must be separately metered and declared to the RLDC/RPC; it rejects the 1 MW draft, settling on stations of 5 MW and above but below 50 MW, with anything smaller left to captive consumption and RECs (p5–6). CTU's objection to the 'transmission capacity margin' wording is accepted (p6).

Scheduling (pp6–7) brings these stations under the IEGC and directs a finer availability-declaration resolution pending an IEGC amendment. Principal Generator (pp7–9) creates the central new concept: the host station acts operationally and commercially for the renewable station(s) under a written agreement filed with CTU and RLDC. Later sections dispose of metering boundaries and loss liability (p9), transmission charges for solar (p9), control area and meter-reading/accounting arrangements (pp9–10), RLDC fees (p10), captive RE at ISTS substations and RECs (p10), gaming (p10) and tariff treatment of shared land and evacuation assets (pp10–11). Paragraphs 31–32 give the amended text.

Standard name
Connectivity and GNA Regulations
Primary topics
Connectivity and GNA, Metering, Scheduling and despatch

Read with this

Other copies of these documents (7)

Earlier drafts

4 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗