CERC · Central Electricity Regulatory Commission
Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022
Central Electricity Regulatory Commission (Connectivity and General Network Access to the inter-State Transmission System) Regulations, 2022
Regulation · Gazette copyDated 7 Jun 2022Published in the Gazette 19 Jul 2022No. L-1/261/2021/CERC.— dated the 7th June, 2022
The Gazette copy of the Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022.
Summary
Summary written by software, from pages 1 to 45 of 56. Check the regulator's original before you rely on it.
The document is the Central Electricity Regulatory Commission (Connectivity and General Network Access to the inter-State Transmission System) Regulations, 2022, issued by CERC and published in the Gazette of India (p1, p30). It creates a consolidated framework for non-discriminatory open access to the inter-State transmission system (ISTS), moving from the earlier connectivity/long-term access approach to General Network Access (GNA) and Temporary GNA (T-GNA) (p30). It applies across India to entities seeking or holding ISTS connectivity/access, and assigns procedural roles to CTU, NLDC, RLDC, SLDC, STU, power exchanges and transmission licensees (p30–45).
Chapter 1 defines the core vocabulary — Connectivity, GNA, T-GNA, ATS, Lead Generator, Lead ESS, ESS, REGS, NOAR and Nodal Agency — and says the regulations commence on a date CERC notifies, with different dates possible for different provisions (p30–32). Chapter 2 specifies application routes, fees, deficiency handling, withdrawal forfeitures and priority among connectivity applications (p32–33).
Chapter 3 (p33–38) sets eligibility thresholds for Connectivity; application contents; CTU interconnection study and ATS identification; in-principle and final grants; the three-part Connectivity Bank Guarantee (Conn-BG1, Conn-BG2 by terminal-bay voltage, Conn-BG3 by MW); the Connectivity Agreement; monitoring; construction and ownership of dedicated lines and terminal bays; interface meters; transfer/splitting of connectivity; and return or encashment of bank guarantees.
Chapter 4 (p38–41) covers GNA eligibility, deemed GNA for STUs and other grid-connected entities based on historical drawal (Annexure-I, p28–29), additional GNA applications by STU and non-STU entities, system study, grant timelines, effective dates, and use of one grantee’s GNA by another. Chapter 5 (p41–42) provides for relinquishment of Connectivity and GNA, including charges. Chapter 6 (p42–45) establishes T-GNA, the National Open Access Registry (NOAR), application categories (advance/exigency for bilateral, power exchange for collective), and processing/priority rules. References in the text show later provisions on standing clearance, scheduling and detailed procedures (Regs 31, 33, 37, 39).
Read with this
The regulation
Amendments and corrections
- Dated 18 Jun 2022Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — Corrigendum
- Dated 1 Apr 2023Connectivity and General Network Access to the inter-State Transmission System (First Amendment) Regulations, 2023
- Dated 31 Aug 2023Corrigendum to the Order dated 14 October 2022 on the Detailed Procedure for Connectivity and GNA
- Dated 19 Jun 2024Connectivity and GNA Regulations, 2022 — Second Amendment, 2024
- Dated 31 Aug 2025Connectivity and GNA to the inter-State Transmission System Regulations, 2022 — Third Amendment, 2025
- Dated 4 Nov 2025Connectivity and General Network Access (Third Amendment) Regulations, 2025 — Corrigendum
- Dated 4 Nov 2025Connectivity and GNA Third Amendment Regulations, 2025 — Corrigendum
- Dated 11 Nov 2026Connectivity and General Network Access to the inter-State Transmission System (Fourth Amendment) Regulations, 2026
Commencement notices and reasons
- Dated 9 Oct 2022Gazette - effective date 15.10.2022
- Dated 9 Oct 2022Notification — effective date 15.10.2022
- Dated 1 Apr 2023GNA Regulations commencement notification — effective date 5.4.2023
- Dated 1 Apr 2023Gazette — effective date 5.4.2023
- Dated 3 Aug 2023GNA Regulations, 2022 and First Amendment Regulations, 2023 — commencement notification, effective 1.10.2023
- Dated 3 Aug 2023GNA Regulations, 2022 — commencement notification, effective 1.10.2023
- Dated 4 Jul 2024Gazette — effective date 15.07.2024 (Gazette No. 518)
- Dated 4 Jul 2024Connectivity and GNA Second Amendment Regulations, 2024 — commencement notification
- Dated 31 Jul 2024Connectivity and GNA Regulations, 2022 — First Amendment, 2023 — Statement of Reasons
Procedures and orders made under it
- Dated 14 Oct 2022Approval of Detailed Procedure for Connectivity and GNA under the GNA Regulations, 2022
- Dated 22 Sep 2023Connectivity and GNA Regulations, 2022 — Removal of Difficulties (First Order), 2023
- Dated 29 Sep 2023Connectivity and General Network Access Regulations, 2022 — Removal of Difficulties (Second Order), 2023
- Dated 29 Sep 2023Detailed Procedure for Allocation of Transmission Corridor for GNA and T-GNA Scheduling under GNA Regulations, 2022 — 2023
- Dated 1 Oct 2023Connectivity and GNA Regulations, 2022 — Removal of Difficulties (Third Order), 2023
- Dated 7 Oct 2023Connectivity and General Network Access Regulations, 2022 — Fourth Removal of Difficulties Order
- Dated 8 Dec 2025Connectivity and General Network Access Regulations, 2022 — Removal of Difficulties Order, 2025
- Dated 4 May 2026Approval of Detailed Procedure for metering, accounting and scheduling of entities under the GNA Regulations, 2022
- Dated 25 May 2026Approval of Detailed Procedure for Declaration of State-wise Solar and Non-solar Hours under the GNA Regulations
- Dated 9 Jun 2026Procedure in respect of Regulation 11C of the Connectivity and General Network Access Regulations, 2022 — Approval Order
- Dated 10 Jul 2026Treatment of LoA-based Connectivity under GNA Regulations, 2026 — Order
- Dated 14 Aug 2026Procedure for Levying Compensation Charges for Additional Time to Achieve Milestones under the GNA Regulations, 2022
Consolidated copies, for reference (1)
Other copies of these documents (4)
- Dated 1 Apr 2023Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — First Amendment, 2023
- Dated 19 Jun 2024Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — Second Amendment, 2024
- Dated 31 Aug 2025Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — Third Amendment, 2025
- Dated 11 Nov 2026Connectivity and General Network Access to the inter-State Transmission System (Fourth Amendment) Regulations, 2026
Earlier drafts
- Dated 27 Jan 2022Workshop notice on Draft Connectivity and General Network Access Regulations, 2021
- Dated 16 Dec 2021File: Connectivity and General Network Access to the inter-State Transmission System Regulations, 2021 — Draft
- Dated 16 Dec 2021Notice extending the date for comments: Public Notice on Draft Connectivity and General Network Access to the inter-State Transmission System Regulations, 2021
- Dated 14 Jan 2022Notice extending the date for comments: Draft Connectivity and GNA Regulations, 2021 — Public Notice (Extension-I) — comments deadline extended
- Dated 26 Jan 2022Explanatory memorandum: Draft Connectivity and GNA Regulations, 2021 — Explanatory Memorandum
- Dated 16 Feb 2022Hearing notice: Public hearing notice on Draft Connectivity and General Network Access Regulations, 2021 — hearing 07.03.2022
- Dated 16 Feb 2022Notice extending the date for comments: Draft Connectivity and General Network Access to the inter-State Transmission System Regulations, 2021 — Comments Deadline Extension-II, 2022
- Dated 27 Jan 2023Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — First Amendment, 2023 — Draft
- Dated 27 Jan 2023Notice extending the date for comments: Connectivity and General Network Access (First Amendment) Regulations, 2023 — Public Notice — Draft
- Dated 13 Feb 2023Explanatory memorandum: Connectivity and General Network Access (First Amendment) Regulations, 2022 — Explanatory Memorandum — Draft
- Dated 16 Feb 2023Notice extending the date for comments: Public Notice — Extension of Comments Deadline on Draft Connectivity and General Network Access (First Amendment) Regulations, 2023
- Dated 27 Feb 2023Hearing notice: Public hearing notice — Draft Connectivity and General Network Access (First Amendment) Regulations, 2023
- Dated 16 Feb 2024Connectivity and General Network Access to the inter-State Transmission System (Second Amendment) Regulations, 2024 — Draft
- Dated 16 Feb 2024Public notice: Connectivity and General Network Access (Second Amendment) Regulations, 2024 — Public Notice — Draft
- Dated 5 Mar 2024Explanatory memorandum: Draft Connectivity and General Network Access to the inter-State Transmission System (Second Amendment) Regulations, 2023 — Explanatory Memorandum
- Dated 13 Mar 2024Hearing notice: Public hearing notice — Connectivity and General Network Access (Second Amendment) Regulations, 2024
- Dated 31 Jul 2024Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — Third Amendment, 2024 — Draft
- Dated 31 Jul 2024Explanatory memorandum: Connectivity and General Network Access (Third Amendment) Regulations, 2024 — Explanatory Memorandum — Draft
- Dated 31 Jul 2024Public notice: Draft Connectivity and General Network Access (Third Amendment) Regulations, 2024 — Public Notice
- Dated 30 Aug 2024Notice extending the date for comments: Connectivity and General Network Access (Third Amendment) Regulations, 2024 — Extension of comment deadline — Public Notice
- Dated 26 Sep 2024Hearing notice: Connectivity and General Network Access (Third Amendment) Regulations, 2024 — public hearing notice
- Dated 3 Mar 2025Connectivity and General Network Access to the inter-State Transmission System (Fourth Amendment) Regulations, 2025 — Draft
- Dated 3 Mar 2025Public notice: Connectivity and GNA (Fourth Amendment) Regulations, 2025 — Draft — Public Notice
- Dated 12 Mar 2025Explanatory memorandum: Connectivity and GNA Regulations, 2022 — Fourth Amendment, 2025 — Explanatory Memorandum — Draft
- Dated 28 Mar 2025Hearing notice: Public hearing notice on Draft Connectivity and General Network Access (Fourth Amendment) Regulations, 2025
- Dated 15 Apr 2026GNA Milestone Extension Compensation Procedure, 2022 — Draft
- Dated 1 May 2026Notice extending the date for comments: Public hearing notice on GNA milestone-extension compensation charges under the Connectivity and GNA Regulations, 2022
- Dated 6 May 2026Treatment of GNA LoA-Route Connectivity Where PPA Not Signed Within 12 Months — Draft Order, 2026
- Dated 13 May 2026Hearing notice: Public hearing notice — GNA connectivity where PPA not signed within 12 months of LoA, 2026
- Dated 20 May 2026Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — Fourth Amendment, 2026 — Draft
- Dated 20 May 2026Public notice: Connectivity and GNA (Fourth Amendment) Regulations, 2026 — Public Notice — Draft
- Dated 2 Jun 2026Hearing notice: Public hearing notice on Draft Connectivity and General Network Access (Fourth Amendment) Regulations, 2026
- Dated 16 Jun 2026Explanatory memorandum: Connectivity and GNA (Fourth Amendment) Regulations, 2026 — Explanatory Memorandum — Draft
- Dated 22 Jun 2026Notice extending the date for comments: Connectivity and GNA (Fourth Amendment) Regulations, 2024 — comment deadline extension notice
16 more documents belong here and are not on Voltaic: 12 drafts or notices on a draft not held as English text and 4 drafts or notices on a draft.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.