CERC · Central Electricity Regulatory Commission
Connectivity and GNA (Fourth Amendment) Regulations, 2026 — Explanatory Memorandum — Draft
Explanatory Memorandum of Draft CERC (Connectivity and General Network Access to the inter-State Transmission System) (Fourth Amendment) Regulations, 2026
Explanatory memorandum to a draftDated 16 Jun 2026No. L-1/261/2021/CERC dated 16.06.2026
Draft
The draft has since been finalised as the Connectivity and General Network Access to the inter-State Transmission System (Fourth Amendment) Regulations, 2026.
Explanatory memorandum to the Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — Fourth Amendment, 2026 — Draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is CERC's explanatory memorandum for the draft Fourth Amendment to the Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — file No. L-1/261/2021/CERC, dated 16 June 2026 (p1). It is not the amendment itself: it explains, part by part, why each change is proposed and reproduces the text proposed to be inserted or substituted, drawing on stakeholder letters, CTUIL's submissions, suo motu orders and a Ministry of Power meeting.
The background (pp1–3) records the parent GNA Regulations of 7 June 2022 with their first three amendments, and lists 29 broad proposals (a) to (cc) that the memorandum then explains. The driving problem, set out at pp5–10, is that CTUIL has granted in-principle connectivity on tentative systems it cannot convert into final grants — about 128 GW of backlog, with roughly 33 GW in Rajasthan, Gujarat and Maharashtra lacking an identified system (p7).
The first substantive block changes the grant process. A new Regulation 3.10, with amendments to Regulations 6.3 and 7.2 (pp5–10), would issue an in-principle grant only after the identified augmentation is approved, allow the Nodal Agency to close applications where no transmission system can be planned, and let a grantee withdraw its full connectivity quantum with return of all Conn-BGs and Land BG where the gap between the likely start date in the in-principle grant and the start date in the final grant is two years or more, if it asks within 30 days of the final grant (p5, p10).
A second block covers storage and additional capacity: ESS seeking full-day or non-solar-hour access would need a minimum discharge of twice the connectivity quantum (Regulations 4.1, 5.2 and 5.4; p11); a new Regulation 4.7 allows non-solar-hour-only access at locations outside the Annexure-IV list (pp11–12); capacity installed for point-of-injection technical compliance is excluded from installed capacity (pp12–13); and Regulation 5.2 gains conditions on application fee, Land BG by the implementing entity, REGS installed solely to charge an ESS, and revocation cascading from the original grantee (pp13–16). A single LoA/PPA may be used for connectivity at several locations up to the LoA/PPA quantum, with location-specific SCOD (pp18–22).
Land, milestone and guarantee provisions are then restructured: 'Land BG' is defined, the ESS (excluding PSP) Land BG is reduced, LoA/PPA holders must file land documents after GNA effectiveness, financial-closure filing is consolidated into a single 15-day post-effectiveness requirement, route conversion from the land/Land-BG route is allowed only on a PPA and not on an LoA, change of source is permitted twice (the second at a fee), change-of-control approval is extended to in-principle grantees, and Conn-BG2 and Conn-BG3 are returned one year after COD with a transition clause (pp4, 17, 23–34).
Institutional and commercial parts add dual connectivity for drawee entities to ISTS and intra-state/distribution systems, subject to STU consent, GNA-only (not GNARE) and technical studies (pp34–39); move one-time GNA charges to 15 days after GNA effectiveness with a bar on grid transactions if unpaid and no BG subsists (pp39–40); recognise CTU's completion certificate for regulated-tariff-mechanism elements for GNA effectiveness (pp40–41); and permit transfer of GNA along with the load sold (pp41–42).
Finally, the draft deletes the cross-border provisions from the GNA Regulations to follow the Cross Border Trade of Electricity (Second Amendment) Regulations, 2025 (pp42–43), sets a common processing timeline where source-change, Regulation 5.2 and Regulation 5.11 applications arrive at one substation in the same month (pp43–44), and amends Regulation 39.1 so the CTUIL Detailed Procedure can be revised (p44).
Read with this
The regulation
Amendments and corrections
- Dated 18 Jun 2022Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — Corrigendum
- Dated 1 Apr 2023Connectivity and General Network Access to the inter-State Transmission System (First Amendment) Regulations, 2023
- Dated 31 Aug 2023Corrigendum to the Order dated 14 October 2022 on the Detailed Procedure for Connectivity and GNA
- Dated 19 Jun 2024Connectivity and GNA Regulations, 2022 — Second Amendment, 2024
- Dated 31 Aug 2025Connectivity and GNA to the inter-State Transmission System Regulations, 2022 — Third Amendment, 2025
- Dated 4 Nov 2025Connectivity and General Network Access (Third Amendment) Regulations, 2025 — Corrigendum
- Dated 4 Nov 2025Connectivity and GNA Third Amendment Regulations, 2025 — Corrigendum
- Dated 11 Nov 2026Connectivity and General Network Access to the inter-State Transmission System (Fourth Amendment) Regulations, 2026
Commencement notices and reasons
- Dated 9 Oct 2022Gazette - effective date 15.10.2022
- Dated 9 Oct 2022Notification — effective date 15.10.2022
- Dated 1 Apr 2023GNA Regulations commencement notification — effective date 5.4.2023
- Dated 1 Apr 2023Gazette — effective date 5.4.2023
- Dated 3 Aug 2023GNA Regulations, 2022 and First Amendment Regulations, 2023 — commencement notification, effective 1.10.2023
- Dated 3 Aug 2023GNA Regulations, 2022 — commencement notification, effective 1.10.2023
- Dated 4 Jul 2024Gazette — effective date 15.07.2024 (Gazette No. 518)
- Dated 4 Jul 2024Connectivity and GNA Second Amendment Regulations, 2024 — commencement notification
- Dated 31 Jul 2024Connectivity and GNA Regulations, 2022 — First Amendment, 2023 — Statement of Reasons
Procedures and orders made under it
- Dated 14 Oct 2022Approval of Detailed Procedure for Connectivity and GNA under the GNA Regulations, 2022
- Dated 22 Sep 2023Connectivity and GNA Regulations, 2022 — Removal of Difficulties (First Order), 2023
- Dated 29 Sep 2023Connectivity and General Network Access Regulations, 2022 — Removal of Difficulties (Second Order), 2023
- Dated 29 Sep 2023Detailed Procedure for Allocation of Transmission Corridor for GNA and T-GNA Scheduling under GNA Regulations, 2022 — 2023
- Dated 1 Oct 2023Connectivity and GNA Regulations, 2022 — Removal of Difficulties (Third Order), 2023
- Dated 7 Oct 2023Connectivity and General Network Access Regulations, 2022 — Fourth Removal of Difficulties Order
- Dated 8 Dec 2025Connectivity and General Network Access Regulations, 2022 — Removal of Difficulties Order, 2025
- Dated 4 May 2026Approval of Detailed Procedure for metering, accounting and scheduling of entities under the GNA Regulations, 2022
- Dated 25 May 2026Approval of Detailed Procedure for Declaration of State-wise Solar and Non-solar Hours under the GNA Regulations
- Dated 9 Jun 2026Procedure in respect of Regulation 11C of the Connectivity and General Network Access Regulations, 2022 — Approval Order
- Dated 10 Jul 2026Treatment of LoA-based Connectivity under GNA Regulations, 2026 — Order
- Dated 14 Aug 2026Procedure for Levying Compensation Charges for Additional Time to Achieve Milestones under the GNA Regulations, 2022
Consolidated copies, for reference (1)
Other copies of these documents (5)
- Dated 7 Jun 2022Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022
- Dated 1 Apr 2023Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — First Amendment, 2023
- Dated 19 Jun 2024Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — Second Amendment, 2024
- Dated 31 Aug 2025Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — Third Amendment, 2025
- Dated 11 Nov 2026Connectivity and General Network Access to the inter-State Transmission System (Fourth Amendment) Regulations, 2026
Earlier drafts
- Dated 27 Jan 2022Workshop notice on Draft Connectivity and General Network Access Regulations, 2021
- Dated 16 Dec 2021File: Connectivity and General Network Access to the inter-State Transmission System Regulations, 2021 — Draft
- Dated 16 Dec 2021Notice extending the date for comments: Public Notice on Draft Connectivity and General Network Access to the inter-State Transmission System Regulations, 2021
- Dated 14 Jan 2022Notice extending the date for comments: Draft Connectivity and GNA Regulations, 2021 — Public Notice (Extension-I) — comments deadline extended
- Dated 26 Jan 2022Explanatory memorandum: Draft Connectivity and GNA Regulations, 2021 — Explanatory Memorandum
- Dated 16 Feb 2022Hearing notice: Public hearing notice on Draft Connectivity and General Network Access Regulations, 2021 — hearing 07.03.2022
- Dated 16 Feb 2022Notice extending the date for comments: Draft Connectivity and General Network Access to the inter-State Transmission System Regulations, 2021 — Comments Deadline Extension-II, 2022
- Dated 27 Jan 2023Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — First Amendment, 2023 — Draft
- Dated 27 Jan 2023Notice extending the date for comments: Connectivity and General Network Access (First Amendment) Regulations, 2023 — Public Notice — Draft
- Dated 13 Feb 2023Explanatory memorandum: Connectivity and General Network Access (First Amendment) Regulations, 2022 — Explanatory Memorandum — Draft
- Dated 16 Feb 2023Notice extending the date for comments: Public Notice — Extension of Comments Deadline on Draft Connectivity and General Network Access (First Amendment) Regulations, 2023
- Dated 27 Feb 2023Hearing notice: Public hearing notice — Draft Connectivity and General Network Access (First Amendment) Regulations, 2023
- Dated 16 Feb 2024Connectivity and General Network Access to the inter-State Transmission System (Second Amendment) Regulations, 2024 — Draft
- Dated 16 Feb 2024Public notice: Connectivity and General Network Access (Second Amendment) Regulations, 2024 — Public Notice — Draft
- Dated 5 Mar 2024Explanatory memorandum: Draft Connectivity and General Network Access to the inter-State Transmission System (Second Amendment) Regulations, 2023 — Explanatory Memorandum
- Dated 13 Mar 2024Hearing notice: Public hearing notice — Connectivity and General Network Access (Second Amendment) Regulations, 2024
- Dated 31 Jul 2024Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — Third Amendment, 2024 — Draft
- Dated 31 Jul 2024Explanatory memorandum: Connectivity and General Network Access (Third Amendment) Regulations, 2024 — Explanatory Memorandum — Draft
- Dated 31 Jul 2024Public notice: Draft Connectivity and General Network Access (Third Amendment) Regulations, 2024 — Public Notice
- Dated 30 Aug 2024Notice extending the date for comments: Connectivity and General Network Access (Third Amendment) Regulations, 2024 — Extension of comment deadline — Public Notice
- Dated 26 Sep 2024Hearing notice: Connectivity and General Network Access (Third Amendment) Regulations, 2024 — public hearing notice
- Dated 3 Mar 2025Connectivity and General Network Access to the inter-State Transmission System (Fourth Amendment) Regulations, 2025 — Draft
- Dated 3 Mar 2025Public notice: Connectivity and GNA (Fourth Amendment) Regulations, 2025 — Draft — Public Notice
- Dated 12 Mar 2025Explanatory memorandum: Connectivity and GNA Regulations, 2022 — Fourth Amendment, 2025 — Explanatory Memorandum — Draft
- Dated 28 Mar 2025Hearing notice: Public hearing notice on Draft Connectivity and General Network Access (Fourth Amendment) Regulations, 2025
- Dated 15 Apr 2026GNA Milestone Extension Compensation Procedure, 2022 — Draft
- Dated 1 May 2026Notice extending the date for comments: Public hearing notice on GNA milestone-extension compensation charges under the Connectivity and GNA Regulations, 2022
- Dated 6 May 2026Treatment of GNA LoA-Route Connectivity Where PPA Not Signed Within 12 Months — Draft Order, 2026
- Dated 13 May 2026Hearing notice: Public hearing notice — GNA connectivity where PPA not signed within 12 months of LoA, 2026
- Dated 20 May 2026Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — Fourth Amendment, 2026 — Draft
- Dated 20 May 2026Public notice: Connectivity and GNA (Fourth Amendment) Regulations, 2026 — Public Notice — Draft
- Dated 2 Jun 2026Hearing notice: Public hearing notice on Draft Connectivity and General Network Access (Fourth Amendment) Regulations, 2026
- Dated 22 Jun 2026Notice extending the date for comments: Connectivity and GNA (Fourth Amendment) Regulations, 2024 — comment deadline extension notice
16 more documents belong here and are not on Voltaic: 12 drafts or notices on a draft not held as English text and 4 drafts or notices on a draft.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.