Connectivity and GNA (Fourth Amendment) Regulations, 2026 — Explanatory Memorandum — Draft

Explanatory Memorandum of Draft CERC (Connectivity and General Network Access to the inter-State Transmission System) (Fourth Amendment) Regulations, 2026

Explanatory memorandum to a draftDated 16 Jun 2026No. L-1/261/2021/CERC dated 16.06.2026

Explanatory memorandum to the Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — Fourth Amendment, 2026 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's explanatory memorandum for the draft Fourth Amendment to the Connectivity and General Network Access to the inter-State Transmission System Regulations, 2022 — file No. L-1/261/2021/CERC, dated 16 June 2026 (p1). It is not the amendment itself: it explains, part by part, why each change is proposed and reproduces the text proposed to be inserted or substituted, drawing on stakeholder letters, CTUIL's submissions, suo motu orders and a Ministry of Power meeting.

The background (pp1–3) records the parent GNA Regulations of 7 June 2022 with their first three amendments, and lists 29 broad proposals (a) to (cc) that the memorandum then explains. The driving problem, set out at pp5–10, is that CTUIL has granted in-principle connectivity on tentative systems it cannot convert into final grants — about 128 GW of backlog, with roughly 33 GW in Rajasthan, Gujarat and Maharashtra lacking an identified system (p7).

The first substantive block changes the grant process. A new Regulation 3.10, with amendments to Regulations 6.3 and 7.2 (pp5–10), would issue an in-principle grant only after the identified augmentation is approved, allow the Nodal Agency to close applications where no transmission system can be planned, and let a grantee withdraw its full connectivity quantum with return of all Conn-BGs and Land BG where the gap between the likely start date in the in-principle grant and the start date in the final grant is two years or more, if it asks within 30 days of the final grant (p5, p10).

A second block covers storage and additional capacity: ESS seeking full-day or non-solar-hour access would need a minimum discharge of twice the connectivity quantum (Regulations 4.1, 5.2 and 5.4; p11); a new Regulation 4.7 allows non-solar-hour-only access at locations outside the Annexure-IV list (pp11–12); capacity installed for point-of-injection technical compliance is excluded from installed capacity (pp12–13); and Regulation 5.2 gains conditions on application fee, Land BG by the implementing entity, REGS installed solely to charge an ESS, and revocation cascading from the original grantee (pp13–16). A single LoA/PPA may be used for connectivity at several locations up to the LoA/PPA quantum, with location-specific SCOD (pp18–22).

Land, milestone and guarantee provisions are then restructured: 'Land BG' is defined, the ESS (excluding PSP) Land BG is reduced, LoA/PPA holders must file land documents after GNA effectiveness, financial-closure filing is consolidated into a single 15-day post-effectiveness requirement, route conversion from the land/Land-BG route is allowed only on a PPA and not on an LoA, change of source is permitted twice (the second at a fee), change-of-control approval is extended to in-principle grantees, and Conn-BG2 and Conn-BG3 are returned one year after COD with a transition clause (pp4, 17, 23–34).

Institutional and commercial parts add dual connectivity for drawee entities to ISTS and intra-state/distribution systems, subject to STU consent, GNA-only (not GNARE) and technical studies (pp34–39); move one-time GNA charges to 15 days after GNA effectiveness with a bar on grid transactions if unpaid and no BG subsists (pp39–40); recognise CTU's completion certificate for regulated-tariff-mechanism elements for GNA effectiveness (pp40–41); and permit transfer of GNA along with the load sold (pp41–42).

Finally, the draft deletes the cross-border provisions from the GNA Regulations to follow the Cross Border Trade of Electricity (Second Amendment) Regulations, 2025 (pp42–43), sets a common processing timeline where source-change, Regulation 5.2 and Regulation 5.11 applications arrive at one substation in the same month (pp43–44), and amends Regulation 39.1 so the CTUIL Detailed Procedure can be revised (p44).

Standard name
Connectivity and GNA Regulations
Primary topics
Connectivity and GNA, Network planning and investment, Energy storage deployment

Read with this

Procedures and orders made under it

Consolidated copies, for reference (1)

Other copies of these documents (5)

Earlier drafts

16 more documents belong here and are not on Voltaic: 12 drafts or notices on a draft not held as English text and 4 drafts or notices on a draft.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document