TNERC · Tamil Nadu Electricity Regulatory Commission
Tamil Nadu Electricity Distribution Code — Agricultural Service Connection Amendments, 2020
Amendments to the Tamil Nadu Electricity Distribution Code
AmendmentDated 16 Jul 2020Published in the Gazette 5 Aug 2020TNERC/DC/8-27 dated 16-07-2020
Amends the Tamil Nadu Electricity Supply Code (TNESC).
Summary
Summary written by software. Check the regulator's original before you rely on it.
This Tamil Nadu Government Gazette notification (No. 32, Part VI—Section 2, dated 5 August 2020, p1) carries two TNERC amendment sets: one to the Tamil Nadu Electricity Supply Code and one to the Tamil Nadu Electricity Distribution Code. The Supply Code amendment survives here only as a fragment on p2, dealing with shifting an agricultural well/bore-well service connection to a new location — conditions where the well is co-owned, that shifting is considered irrespective of the consumer's reason or whether the well still exists, and that a fresh Form-2 application, shifting charges and a new agreement are required before the licensee takes up work.
The Distribution Code amendment (Notification No. TNERC/DC/8-27 dated 16-07-2020, made under s.181 read with s.46 of the Electricity Act 2003) is the substantive body. It rewrites regulation 27(2) into a step-by-step registration and processing procedure for normal-category agricultural applications: registration with a seniority number, written intimation of seniority, a 90-day notice to re-confirm particulars before an estimate is prepared, entry in a readiness register, extension of time up to five years and lapse thereafter, segregation of works into three categories with priority registers, 30-day supply notices, and cancellation plus dismantling of licensee-erected works if supply is not availed within six months (p2–4). The procedure applies only to the 'normal category'; licensees must frame separate procedures for other categories (p4).
Regulation 29(2) is expanded to govern who may obtain connections within a survey number, co-owner connections, separate non-agricultural pumping connections, and changeover switches with deemed approval after fifteen days (p4). Regulation 31 gains a sub-regulation cross-referring agricultural notices to regulation 27(2) (p4), and Annexure III Form-2 is replaced by a new application form (p5–8). The remainder is explanatory: an Explanatory Statement on why the procedure was simplified (p8) and a side-by-side comparative statement (p9–15).
Read with this
Read with this: Tamil Nadu Electricity Supply Code (TNESC)
The regulation
- Dated 21 Jul 2004Tamil Nadu Electricity Supply Code (TNESC)
Amendments and corrections
- Dated 22 Nov 2005Tamil Nadu Electricity Supply (Amendment) Code 2005 — load addition/reduction, surcharge and BPSC
- Dated 19 May 2006Tamil Nadu Electricity Supply (Amendment) Code 2006
- Dated 20 Sep 2006Tamil Nadu Electricity Supply Code — Explanation on Refund of Tariff Minimum, 2006
- Dated 10 Apr 2007Tamil Nadu Electricity Supply (Amendment) Code, 2007
- Dated 25 May 2007Tamil Nadu Electricity Supply Code, 2004 — Amendment Code 2007
- Dated 23 Aug 2007Tamil Nadu Electricity Supply Code, 2004 — Second Amendment Code, 2007
- Dated 3 Dec 2007Tamil Nadu Electricity Supply Code, Distribution Code and Standard of Performance (Amendment) Regulations 2007
- Dated 14 Dec 2007Tamil Nadu Electricity Supply Code — Second Amendment, 2007
- Dated 6 Jun 2008Tamil Nadu Electricity Supply (Amendment) Code 2008
- Dated 31 Jul 2008Tamil Nadu Electricity Supply (Amendment) Code 2008 — disconnection for arrears
- Dated 15 Dec 2008Tamil Nadu Electricity Supply (Amendment) Code, 2008
- Dated 27 Feb 2009Tamil Nadu Electricity Supply Code, 2004 — Amendment Code, 2009
- Dated 15 Jun 2009Tamil Nadu Electricity Supply Code, 2004 — Amendment Code, 2009
- Dated 29 Jun 2009Tamil Nadu Electricity Supply (Amendment) Code 2009
- Dated 9 Oct 2009Amendment to Regulation 19, 20 & 23 of Supply Code
- Dated 29 Dec 2009Tamil Nadu Electricity Supply (Amendment) Code, 2009
- Dated 6 May 2010Tamil Nadu Electricity Supply (Amendment) Code 2010
- Dated 25 Oct 2010Tamil Nadu Electricity Supply Code, 2005 — Amendment Code 2010
- Dated 27 May 2011Tamil Nadu Electricity Supply (Amendment) Code, 2011
- Dated 29 Nov 2012Tamil Nadu Electricity Supply Code Amendment, 2012
- Dated 12 Sep 2013Tamil Nadu Electricity Supply Code — Minimum Charges Amendment, 2013
- Dated 23 Sep 2013Tamil Nadu Electricity Supply Code and State Advisory Committee Regulations — Amendments, 2013
- Dated 26 Nov 2013Tariff Regulations, Distribution Code and Supply Code — Amendments, 2013
- Dated 3 Jun 2014Tamil Nadu Electricity Supply Code, 2004 — Regulation 22 Amendment, 2014
- Dated 1 Jul 2014Tamil Nadu Electricity Supply Code — Amendment to Regulations 4, 5, 7, 15 and 27, 2014
- Dated 5 Nov 2014Tamil Nadu Electricity Supply Code — Errata to Notification, 2014
- Dated 22 Apr 2015Tamil Nadu Electricity Supply Code, 2004 — Mode of Payment Amendment, 2015
- Dated 2 Mar 2018Tamil Nadu Electricity Distribution Code Amendments, 2018
- Dated 2 Mar 2018Tamil Nadu Electricity Supply Code — Amendments, 2018
- Dated 18 Dec 2019Tamil Nadu Electricity Supply Code — Amendments, 2019
- Dated 9 Jun 2020Tamil Nadu Electricity Supply Code and Distribution Code — LT/HT 150 kW Amendment, 2020
- Dated 27 Jun 2020Tamil Nadu Electricity Supply Code, 2004 — Amendment (Regulation 14A, AMR/AMI billing notice)
- Dated 16 Jul 2020Tamil Nadu Electricity Supply Code and Distribution Code — Amendments, 2020
- Dated 24 Dec 2020Tamil Nadu Electricity Supply Code and Distribution Code Amendments, 2021
- Dated 24 Dec 2020Tamil Nadu Electricity Supply Code and Distribution Code Amendment, 2021
- Dated 26 May 2021Tamil Nadu Electricity Supply Code, 2004 — Wheeling and Network Charges Amendment, 2021
- Dated 29 Mar 2022Tamil Nadu Electricity Supply Code, 2004 — Harmonic Control Amendment, 2022
- Dated 26 Jul 2022Tamil Nadu Electricity Supply Code, 2004 — Amendment, 2022
- Dated 2 Sep 2023Tamil Nadu Electricity Supply Code, 2004 — Amendments, 2023
Consolidated copies, for reference (4)
- Dated 31 Jul 2008Tamil Nadu Electricity Supply Code — Consolidated, as amended up to 31.7.2008
- Dated 31 Dec 2009Tamil Nadu Electricity Supply Code (TNESC) — Consolidated, as amended upto 31-12-2009
- Dated 31 Dec 2010Tamil Nadu Electricity Supply Code — Consolidated as amended upto 31-12-2010
- Dated 31 Mar 2024Tamil Nadu Electricity Supply Code — Consolidated as amended up to 31-03-2024
Proposed changes (drafts with no final yet)
Earlier drafts
- Dated 11 Apr 2006Tamil Nadu Electricity Supply Code — 2006 Amendment
- Dated 4 Dec 2009Tamil Nadu Electricity Supply (Amendment) Code, 2009
- Dated 21 Jun 2010Power Procurement from New and Renewable Sources of Energy Regulations, 2008 — Amendment, 2010 — Draft
- Dated 13 Jul 2010Tamil Nadu Electricity Supply (Amendment) Code, 2010 — Draft
- Dated 14 Jan 2011Tamil Nadu Electricity Supply (Amendment) Code, 2011 — Draft
- Dated 29 Mar 2011Draft Consultative Paper on Non-Tariff Related Miscellaneous Charges — Supply of CMRI Data to HT Consumers
- Dated 5 Apr 2011Tamil Nadu Electricity Supply Code, 2004 — 2011 Amendment — Draft
- Dated 30 Sep 2011Tamil Nadu Electricity Supply (Amendment) Code, 2011 — Security Deposit for Non-Owner Consumers
- Dated 24 Aug 2012Tamil Nadu Electricity Supply (Amendment) Code, 2012 — Draft
- Dated 28 Jun 2013Tamil Nadu Electricity Supply Code, 2005 — Draft Amendment — Minimum Charges for Disconnected HT Services
- Dated 12 Sep 2013Draft Amendment to Regulation 3 of the Tamil Nadu Electricity Supply Code, 2013
- Dated 27 May 2014Tamil Nadu Electricity Supply Code, 2004 — Additional Security Deposit (Partial Open Access) Amendment, 2014 — Draft
- Dated 7 Jan 2015Tamil Nadu Electricity Supply Code, 2004 — Draft Amendment
- Dated 24 May 2017Tamil Nadu Electricity Supply Code — Power Factor Disincentive Amendment, 2017 — Draft
- Dated 6 Jul 2017Tamil Nadu Electricity Supply Code — Draft Amendment, 2017
- Dated 9 Jul 2019Draft Amendment to the Tamil Nadu Electricity Supply Code, 2019
- Dated 7 Nov 2019Tamil Nadu Electricity Supply Code — Draft Amendment, 2019
- Dated 6 Mar 2020Draft Amendments to the Tamil Nadu Electricity Supply Code, 2020
- Dated 9 Oct 2020Tamil Nadu Electricity Supply Code, 2004 — Power Factor and Minimum Charges Amendment, 2020 — Draft
- Dated 23 Dec 2020Procedure of Assessment where Bi-directional Meter is Defective or Absent — Draft Amendment to the Tamil Nadu Electricity Supply Code, 2004
- Dated 19 Mar 2021Tamil Nadu Electricity Supply Code, 2004 — Draft Amendment (Wheeling Charges)
- Dated 29 Jun 2021Tamil Nadu Electricity Supply Code — Harmonic Limits Amendment, 2021 — Draft
- Dated 9 Jun 2022Tamil Nadu Electricity Supply Code, 2004 — Draft Amendment, 2022
- Dated 28 Jun 2022Tamil Nadu Electricity Supply Code, 2004 — Draft Amendment
- Dated 27 Apr 2023Tamil Nadu Electricity Supply Code, 2004 — Draft Amendments, 2023
32 more documents belong here and are not on Voltaic: 30 copies in another language, 1 corrigendum not held as English text and 1 draft or notice on a draft.
It is also read with: Tamil Nadu Electricity Distribution Code
Amends the Tamil Nadu Electricity Distribution Code.
The regulation
- Dated 21 Jul 2004Tamil Nadu Electricity Distribution Code
Amendments and corrections
- Dated 22 Nov 2005Tamil Nadu Electricity Distribution (Amendment) Code 2005
- Dated 23 Feb 2006Tamil Nadu Electricity Distribution Code, 2004 — 2006 Amendment
- Dated 31 May 2006Tamil Nadu Electricity Distribution Code, 2004 — 2006 Amendment
- Dated 14 Jun 2006Tamil Nadu Electricity Distribution Code 2006 — Amendment — point of supply beyond 30 m
- Dated 22 Jun 2006Tamil Nadu Electricity Distribution (Amendment) Code 2006
- Dated 20 Jul 2006Tamil Nadu Electricity Distribution Code, 2004 — Amendment Code, 2006
- Dated 10 Sep 2007Tamil Nadu Electricity Distribution (Amendment) Code, 2007
- Dated 3 Dec 2007Tamil Nadu Electricity Supply Code, Distribution Code and Standard of Performance (Amendment) Regulations 2007
- Dated 8 Feb 2008Tamil Nadu Electricity Distribution Code, 2004 — First Amendment, 2008
- Dated 22 May 2008Tamil Nadu Electricity Distribution Code — Second Amendment, 2008
- Dated 29 Jun 2009Tamil Nadu Electricity Distribution (Amendment) Code, 2009
- Dated 24 Aug 2009Tamil Nadu Electricity Distribution (Amendment) Code, 2009
- Dated 14 Mar 2011Amendment of Clause 51 of the Principal Code
- Dated 17 Feb 2012Tamil Nadu Electricity Distribution (Amendment) Code 2012
- Dated 29 Nov 2012Tamil Nadu Electricity Distribution Code — Amendment, 2012
- Dated 6 Sep 2013Tamil Nadu Electricity Distribution Code, Regulation 39 (Temporary Supply) — Amendment, 2013
- Dated 26 Nov 2013Tariff Regulations, Distribution Code and Supply Code — Amendments, 2013
- Dated 1 Jul 2014Tamil Nadu Electricity Distribution Code Amendments, 2014
- Dated 11 Sep 2014Tamil Nadu Electricity Distribution Code — Amendment, 2014
- Dated 7 Oct 2014Tamil Nadu Electricity Distribution Code — Amendment, 2014
- Dated 23 Jan 2015Tamil Nadu Electricity Distribution Code — Regulation 8 Substitution, 2015
- Dated 30 Aug 2017Tamil Nadu Electricity Distribution Code — FORM-4 Amendment, 2017
- Dated 2 Mar 2018Tamil Nadu Electricity Distribution Code Amendments, 2018
- Dated 18 Dec 2019Tamil Nadu Electricity Distribution Code — Amendment, 2019
- Dated 9 Jun 2020Tamil Nadu Electricity Distribution Code — Amendment to Regulation 26(1)(b), 2020
- Dated 9 Jun 2020Tamil Nadu Electricity Supply Code and Distribution Code — LT/HT 150 kW Amendment, 2020
- Dated 16 Jul 2020Tamil Nadu Electricity Supply Code and Distribution Code — Amendments, 2020
- Dated 24 Dec 2020Tamil Nadu Electricity Supply Code and Distribution Code Amendments, 2021
- Dated 24 Dec 2020Tamil Nadu Electricity Supply Code and Distribution Code Amendment, 2021
- Dated 2 Sep 2023Tamil Nadu Electricity Distribution Code, 2004 — Amendments, 2023
Consolidated copies, for reference (4)
- Dated 31 Jul 2008Tamil Nadu Electricity Distribution Code — Consolidated re-publication as amended up to 31.07.2008
- Dated 31 Dec 2009Tamil Nadu Electricity Distribution Code, as amended up to 31.12.2009 — Consolidated
- Dated 31 Dec 2010Tamil Nadu Electricity Distribution Code — Consolidated re-publication, as amended up to 31-12-2010
- Dated 31 Mar 2024Tamil Nadu Electricity Distribution Code — Consolidated, as amended upto 31-03-2024
Proposed changes (drafts with no final yet)
Earlier drafts
- Dated 5 Dec 2012Tamil Nadu Electricity Distribution Code — Draft Amendment (Regulation 38 — Restrictions on Use of Electricity)
- Dated 17 Jul 2013Tamil Nadu Electricity Distribution Code — Regulation 39 Temporary Supply Amendment, 2013 — Draft
- Dated 12 May 2014Draft amendments to the Distribution Code and Supply Code on agricultural supply, 2014
- Dated 25 Mar 2015Tamil Nadu Electricity Supply Code and Distribution Code — Draft Amendments, 2015
- Dated 9 Jul 2019Tamil Nadu Electricity Distribution Code, 2019 — Draft Amendments
- Dated 7 Nov 2019Draft Amendment to the Tamil Nadu Electricity Distribution Code, 2019 — Categories of Supply (Regulation 26)
- Dated 6 Mar 2020Draft Amendment to the Tamil Nadu Electricity Distribution Code — Agricultural Service Connections
- Dated 9 Oct 2020Draft Tamil Nadu Electricity Distribution Code Amendment, 2020
- Dated 27 Apr 2023Tamil Nadu Electricity Distribution Code, 2004 — Draft Amendment, 2023
25 more documents belong here and are not on Voltaic: 25 copies in another language.
Voltaic last read TNERC's website for final documents on 29 Sep 2026 and for drafts on 24 Nov 2026. A document TNERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.